# Pre-Takeoff Confirmation
|
|
|
|
The purpose of the pre-takeoff confirmation
|
|
is to address potential discrepancies
|
|
between the requirements of the project documents
|
|
and the scope included in the bid team's proposed price.
|
|
|
|
> [!important]
|
|
> Complete [[pre-takeoff-research]]
|
|
> before sending the confirmation.
|
|
|
|
> [!example] Example provided by Joel Jansen 2025-09-18, edited
|
|
> Good morning,
|
|
>
|
|
> Please see below and confirm the documents we plan to use
|
|
> while we takeoff Alta Watkins are correct.
|
|
>
|
|
> * Plans & Specs,
|
|
> * Drawings: GMP, 2025-09-11
|
|
> * Project Manual: GMP Specifications, 2025-09-11
|
|
> * Proposal: 2025-07-03
|
|
> * Takeoff Stage: **Full Take Off**
|
|
>
|
|
> Also, please confirm:
|
|
>
|
|
> 1. Are there any variations from the drawings that we need to include in our takeoff?
|
|
> 2. Any accepted/pending alternates?
|
|
>
|
|
> Feeders:
|
|
> * Size per Schedule on drawings (AL +100 A).
|
|
> * PVC UG, EMT OH.
|
|
>
|
|
> Subfeeds:
|
|
> * MC for metal stud units, SER all other units
|
|
>
|
|
> Voltage Drop: As shown for subfeeds, 2% Feeders
|
|
>
|
|
> Units:
|
|
> * Devices: Standard Duplex/Toggle
|
|
> * USB Rec's: As shown, plus 1 per bedroom (Type A & C).
|
|
> * Studs: Metal in M units, Wood all other locations.
|
|
> * Telecom: 30" UDP, CAT6. (use 28" in takeoff)
|
|
> * Smoke Detection: 120V
|
|
>
|
|
> Fire Alarm:
|
|
> * Pathways: Free Air
|
|
> * 2-Way: Included
|
|
>
|
|
> Electrical:
|
|
> * Devices: Decora Amenities, Duplex/Toggle BOH
|
|
>
|
|
> Fixtures:
|
|
> * Cable: LV in Amenity Areas
|
|
> * Occupancy Sensors: Local
|
|
>
|
|
> Thank you,
|