- Build Items in Distribution:
- Panelboards
- Switchboards
- Meter centers
- Generators
- Transfer switches
- Generator connection cabinets
- CT cabinets
- Power monitor
- Takeoff Common Assemblies:
- XFMRs
- Disconnect switches
- Takeoff Items in Item Database:
- Wireway (Trough/Gutter)
- Takeoff Temp Assemblies:
- Fire Pump
- Fire Pump Controller
When building panelboards/switchboards, add terminations according to an example from the schedules. Do not include feeder terminations.
[!important] Scope to Exclude
- Tap Boxes
- Bus Duct
- Vault Room
- Anything FPL
- Grounding
- Elevator Room
By Equipment Type
[!tip] When in Doubt If the equipment is not listed below, use a distribution panel of equal amps.
SPD's/TVSS's
Name = "SPD"
Labor only.
Specific item is not important, but I use
SPLITTERS / SOCKETS / CABINETS/METER SOCKETS & CABINETS/METERING CURRENT TRANSFORMER
(Labor = 1.5hrs)
for consistency.
Submeters/Power Monitors
Name = "Power Monitor"
Switchboards
Name = "Switchboard - 2000A, 4-Section"
Panelboards
Name = "Panelboard - 600A, 2-Section"
DISTRIBUTION/DIST PANELS & UNIT LOAD CENTERS/...
Disconnects and Enclosed Circuit Breakers
COMMON ASSEMBLIES/DISTRIBUTION/MANUAL DISCONNECTS/...
Generators
Name = "Generator - 250kW, Diesel"
Add DISTRIBUTION FITTINGS/GENERATOR SET UP.
Generator Connection Cabinets
Name = "GCC - 200A"
Use a Distribution Panel of equal amps. Or a transfer switch.
Transfer Switches
Name = "Transfer Switch - 400A"
Transfer Switches 1200A+
Use 1200A and add an additional TRANSFER SWITCH item
to make up the remaining amps.
Meter Centers
Name = "Meter Center - 800A, 16-Can"
SWITCHGEAR & METER CENTERS/METER CENTERS/... METERING SECTION