PDI Accubid Closeout: Final Price
Material Tax
Calculated % <- Cumulative sales tax at project address.
Markup
Clear markup values from Calculated %:
- "Database Material Markup"
- "Quoted Material Markup"
- "Labor Markup"
- "Adjustment Markup"
Ensure markup was cleared from previous tabs:
- "Subcontractors Markup"
- "General Expenses Markup"
- "Equipment Markup"
Warranty
- Modified ($) <- $0.05 per gross area square foot
CIP
Only if "CIP" is included in Base Bid. See proposal section "Insurance" if present.
Modified ($) <- 0.136% of Contract Value
Selling Price
Modified ($) <- Proposal Base Bid Total