Belle Meade Director Review
estimating-director-review for belle-meade-plaza lead by corwin-fluit, attended by joel-jansen and myself.
Takeoff Review
Reviewed takeoff by system.
Retail Village Temporary Power
Joel changed square foot budgets to temporary pole budgets only due to minimal scope (warm shell).
Generator Scope
Confirmed generator quotes include furnishing docking station.
Feeder Lengths
Confirmed validity of longer feeder lengths: Generator to Tower B
Grounding
Takeoff appears to be missing some or all grounding. To be added if necessary.
Subfeed Sizing
Based on ampacity, subfeeds are oversized. Sizing was per feeder schedule. Takeoff approved unchanged.
Undercabinet Wiremold
Multi-outlet assemblies above unit kitchen countertops were not taken off, nor was branch wiring for the same. Joel to confirm takeoff requirement with bid.
Amenity Homeruns
No homeruns for amenity lighting or electrical were taken off. Joel to add these.
[!info] Circuits per Raceway Corwin stated that---assuming no overriding specification--- up to 6 circuits per raceway are permissible.
Lighting Control
Lighting control takeoff was reviewed, no changes were recommended.
[!info] Lighting Control Pre-Work Corwin stated that with the imminent changes to lighting control takeoff, it will be necessary for estimators to more intently consider the design: noting quantities of lighting zones and controllers, even where not explicitly shown.
Telecom
Confirmed unit telecom requirements.
Backbone was mistakenly taken off in Telecom.
Retail Fire Alarm
Retail village fire alarm devices were taken off free-air, Joel to substitute for EMT.
Extension Review
Reviewed extension quantities and costs. Of particular note were:
- conduit
- wire
- cable
- wiring devices
Labor Plan Review
Hours per square foot was lower than expected, this was rationalized as being due to the relatively high portion of garage and shell retail space.
%% "Openings per unit" was another metric considered--- higher than expected in this case--- however I didn't catch the significance of this. %%