# 2026-02-10 15:49:04
|
|
|
|
## Hampton Roads Navy - Norfolk: Director Review
|
|
|
|
[[estimating-director-review]] of [[hampton-roads-navy_norfolk]]
|
|
lead by [[corwin-fluit]],
|
|
attended by [[christian-pereiro]], [[joel-jansen]], and myself.
|
|
|
|
### Lighting Control
|
|
|
|
* Corridors: $10 per linear foot
|
|
* Amenity: $5 per square foot
|
|
|
|
> Digital lighting control is required
|
|
> * FALSE: Multiple occupancy sensors per zone necessitates digital control.
|
|
> * FALSE: 0-10V dimming necessitates digital control.
|
|
> * FALSE: 0-10V dimming + occupancy sensing necessitates digital control.
|
|
> * TRUE: 0-10V dimming controlled by occupancy sensing necessitates digital control.
|
|
|
|
Systems refused to quote lighting control due to lack of detail,
|
|
but sufficient detail was provided.
|
|
|
|
Bid expected takeoff to include DLM devices and cabling.
|
|
|
|
### Closeout
|
|
|
|
On Base - Newport News is not
|
|
|
|
Carried labor for lost time due to badging
|
|
|
|
#### Equipment
|
|
|
|
> [!quote] Corwin Fluit 2026-02-10
|
|
> `AUGER ON BOBCAT (per pole)` does not include cost for setting pole
|
|
|
|
### Free Notes
|
|
|
|
Ops creates, approves the labor plan.
|
|
This limits our ability to make interesting decisions:
|
|
MC cable ILO PVC in-slab pushes the schedule out.
|
|
|
|
[[estimating-golf]] question, asked by Corwin:
|
|
"Are the electric rooms stacked?"
|
|
|
|
### Thoughts
|
|
|
|
#### Corwin
|
|
|
|
Corwin is a true _estimator_.
|
|
I've met few people more willing to make calculations
|
|
and give confident estimates in conversation.
|
|
|
|
He understands the necessity of accepting and accounting for risk.
|
|
|
|
He is as critical of overly-heavy estimates
|
|
as light estimates.
|
|
He specifically prefers accurate line item costs
|
|
with a single contingency
|
|
over inflated individual budgets.
|