1.7 KiB
id, aliases, tags, title
| id | aliases | tags | title | |||||
|---|---|---|---|---|---|---|---|---|
|
Switchgear |
Switchgear
[!info] See distribution-equipment.
- Build Items in Distribution:
- Panelboards
- Switchboards
- Meter centers
- Generators
- Transfer switches
- Generator connection cabinets
- CT cabinet
- Power monitor
- Takeoff Common Assemblies:
- XFMRs
- Disconnect switches
- Takeoff Items in Item Database:
- Wireway (Trough/Gutter)
- Takeoff Temp Assemblies:
- Fire Pump
- Fire Pump Controller
When building panelboards/switchboards, add terminations according to an example from the schedules. Do not include feeder terminations.
[!important] Scope to Exclude
- Tap Boxes
- Bus Duct
- Vault Room
- Anything FPL
- Grounding
- Elevator Room
SPD's/TVSS's
Labor only.
Specific item is not important, but I use
SPLITTERS / SOCKETS / CABINETS/METER SOCKETS & CABINETS/METERING CURRENT TRANSFORMER
(Labor = 1.5hrs)
for consistency.
Submeters/Power Monitors
Panelboards
DISTRIBUTION/DIST PANELS & UNIT LOAD CENTERS/...
Disconnects and Enclosed Circuit Breakers
COMMON ASSEMBLIES/DISTRIBUTION/MANUAL DISCONNECTS/...
Generators
Add DISTRIBUTION FITTINGS/GENERATOR SET UP.
Generator Connection Cabinets
Use a Distribution Panel of equal amps. Or a transfer switch.
Transfer Switches
"300A ATS"
Transfer Switches 1200A+
Use 1200A and add an additional TRANSFER SWITCH item
to make up the remaining amps.
Meter Centers
SWITCHGEAR & METER CENTERS/METER CENTERS/... METERING SECTION
Adjust Factor 1 for meter stacks, delete zeroed items.