# Switchgear
> [!info]
> See [[distribution-equipment]].
1. Build Items in Distribution:
* Panelboards
* Switchboards
* Meter centers
* Generators
* Transfer switches
* Generator connection cabinets
* CT cabinet
* Power monitor
2. Takeoff Common Assemblies:
* XFMRs
* Disconnect switches
3. Takeoff Items in Item Database:
* Wireway (Trough/Gutter)
4. Takeoff Temp Assemblies:
* Fire Pump
* Fire Pump Controller
When building panelboards/switchboards,
add terminations according to an example from the schedules.
**Do not include feeder terminations.**
> [!important] Scope to Exclude
> * Tap Boxes
> * Bus Duct
> * Vault Room
> * Anything FPL
> * Grounding
> * Elevator Room
## SPD's/TVSS's
Labor only.
Specific item is not important, but I use
`SPLITTERS / SOCKETS / CABINETS`/`METER SOCKETS & CABINETS`/`METERING CURRENT TRANSFORMER`
(Labor = 1.5hrs)
for consistency.
## Submeters/Power Monitors
See [[switchgear#SPD's/TVSS's]]
## Panelboards
`DISTRIBUTION`/`DIST PANELS & UNIT LOAD CENTERS`/...
## Disconnects and Enclosed Circuit Breakers
`COMMON ASSEMBLIES`/`DISTRIBUTION`/`MANUAL DISCONNECTS`/...
## Generators
Add `DISTRIBUTION FITTINGS`/`GENERATOR SET UP`.
## Generator Connection Cabinets
Use a Distribution Panel of equal amps.
Or a transfer switch.
## Transfer Switches
> "300A ATS"
### Transfer Switches 1200A+
Use 1200A and add an additional `TRANSFER SWITCH` item
to make up the remaining amps.
## Meter Centers
`SWITCHGEAR & METER CENTERS`/`METER CENTERS`/`... METERING SECTION`
Adjust Factor 1 for meter stacks, delete zeroed items.