Virginia Live! Internal Review
review of virginia-live-casino-and-hotel accubid job with pdi-operations
Underfloor power is Reloc. Customer is curious if it would be more cost effective to use MC.
Meeting Objective
discuss closeout mainly: quotes and subs.
Topics Discussed
Fixture Labor
Furniture, Fixtures, and Equipment (FF&E)
Concern that all fixtures are captured
"add a line for aiming and testing" 1 week (80 hours)
Shift Rate
"in the past we've paid a little more for night work, but nothing crazy"
Site Services
$2,500 per day scaffold
Ditch witches for most excavation
idea floated to buy equipment rather than rent bobcat wire puller hydraulic bender
Do we own dewatering? pretty sure yes
MV Terminations
No one at PDI can perform MV terms so they must be subbed out
worst case $300k
9 terms $60k
to be quoted by Ops
Testing
primary injection testing
NETA testing
to be quoted by Ops
Rigging
Ops quoted $85k to take one generator off the truck.
to be quoted by Ops
Burden
PTO not included in burden because it is not charged to the job
Admin Housing
Ops paying $4,500 per month for 6-bed
Composite Cleanup
exact terms in contract
Permits
to be quoted by Ops