# Pre-Takeoff Confirmation
|
|
|
|
The purpose of the pre-takeoff confirmation
|
|
is to address potential discrepancies
|
|
between the requirements of the project documents
|
|
and the scope included in the bid team's proposed price.
|
|
|
|
> [!example] Example provided by Joel Jansen 2025-09-18
|
|
> Good morning,
|
|
>
|
|
> Please see below and confirm the documents we plan to use while we takeoff Alta Watkins are correct.
|
|
>
|
|
> * Plans & Specs,
|
|
> * Drawings: GMP, 2025-09-11
|
|
> * Project Manual: GMP Specifications, 2025-09-11
|
|
> * Proposal: 2025-07-03
|
|
>
|
|
> Also, please confirm:
|
|
>
|
|
> 1. Are there any variations from the drawings that we need to include in our takeoff?
|
|
> 2. Any accepted/pending alternates?
|
|
> 3. We are currently taking off **Full Take Off**.
|
|
> 4. Feeders/Subfeeds will be per Schedule on drawings (AL +100 A).
|
|
>
|
|
> * Feeders -- PVC UG, EMT OH.
|
|
> * Subfeeds -- MC for metal stud units, SER all other units.
|
|
> * VD -- As shown for subfeeds, 2% Feeders
|
|
>
|
|
> Units:
|
|
> * Devices -- Standard Duplex/Toggle
|
|
> * USB Rec -- As shown, plus 1 per bedroom (Type A & C).
|
|
> * Studs -- Metal in M units, Wood all other locations.
|
|
> * Telecom -- 30" UDP, CAT6. (use 28" in takeoff)
|
|
> * Smoke Det -- 120V
|
|
>
|
|
> Fire Alarm:
|
|
> * Pathways: Free Air
|
|
> * 2Way: Included
|
|
>
|
|
> Electrical:
|
|
> * Devices: Decora Amenities, Duplex/Toggle BOH
|
|
>
|
|
> Fixtures:
|
|
> * Cable: LV in Amenity Areas
|
|
> * Occupancy Sensor: Local
|
|
>
|
|
> Thank you,
|