Elliot St. ConEst Senior Review
#occupational
%% Transcription of notes taken while reviewing Elliot St. with Joel Jansen. %%
Adorne USB Heating Designation was built with standard device. Subbed for Adorne.
Subbed standard duplex receptacles in guestrooms for Adorne.
Confirmed fixture branch length changes including Garage
Note: It is not usually necessary to count emergency fixtures separately.
Use minimum 1 hour for tape lights, except in units (minimum 0.5hr).
Final Pricing adjustments: Warranty, CIP (see proposal)
Added putty pads.
Fire stopping budget = $25-35 per Unit.
Robotic Total Station hours: match Structural Foreman.
Equipment Cost \approx 1% for contracts 5-15 million dollars.
Mid Atlantic: 1 trip per month
Offsite Parking: see bid sheet
Project Executive time same as Oversight.
When calculating durations for indirect labor, round down.
- Rough Foreman
- Trim Foreman
- Amenity Foreman
LV/FA Foreman: get hours from systems quote.
Fire Alarm, Two-Way Communication, DAS: Phase = "Fire Alarm"
Erroneously used WP GFI's in bathrooms, subbed for Kitchen/Bath assembly.