## Elliot St. ConEst Senior Review
%%
Transcription of notes
taken while observing
[[joel-jansen]]'s [[conest-senior-review]]
of [[elliott-st-hotel]]
%%
Adorne USB Heating Designation was built with standard device.
Subbed for Adorne.
Subbed standard duplex receptacles in guestrooms for Adorne.
Confirmed fixture branch length changes
including Garage
Note: It is not usually necessary to count emergency fixtures separately.
Use minimum 1 hour for tape lights, except in units (minimum 0.5hr).
Final Pricing adjustments:
* Warranty,
* CIP (see proposal)
Added putty pads.
Fire stopping budget = $25-35 per Unit.
Robotic Total Station hours: match Structural Foreman.
For contracts 5--15 million dollars:
Equipment Cost $$\approx$$ 1% of Contract Value
Mid Atlantic: 1 trip per month
Offsite Parking: see bid sheet
Project Executive time same as Oversight.
When calculating durations for indirect labor, round down.
* Rough Foreman
* Trim Foreman
* Amenity Foreman
LV/FA Foreman: get hours from systems quote.
Fire Alarm, Two-Way Communication, DAS: `Phase` = "Fire Alarm"
Erroneously used WP GFI's in bathrooms, subbed for Kitchen/Bath assembly.