id: 2026-05-28T09:17:29-0400
|
|
title: 2026-05-28 09:17:29
|
|
tags: []
|
|
daily: "[[2026-05-28]]"
|
|
---
|
|
# 2026-05-28 09:17:29
|
|
|
|
## Mariposa Spa Electrical
|
|
|
|
[[303-mariposa-residence]]
|
|
|
|
~~E2.01 we have 10 pump connections~~
|
|
~~roughly near where the spa drawings put the pool equipment room~~
|
|
~~not shown on mech, plumbing, otherwise~~
|
|
~~despite Keynote 4 "SEE MECHANICAL WATER PIPING DIAGRAM FOR EXACT LOCATIONS OF PUMPS."~~
|
|
~~We could assume that these are intended for the pool equipment~~
|
|
~~and delete the takeoff.~~[^1]
|
|
|
|
[^1]: M3.00, being a diagram, does not show exact locations,
|
|
_but does show the pumps being used for domestic water._
|
|
(Also the diagram suggests
|
|
that the pumps may be spread much far than implied by Electrical,
|
|
that our takeoff may be missing a large amount of cable.)
|
|
(Also four water heaters are shown
|
|
which were not shown on electrical.)
|
|
|
|
SP400 shows an electrical panel Keynote 16
|
|
|
|
> [!quote] SP400 Keynote 16
|
|
> NOT SHOWN ON PLANS.
|
|
> PROVIDE DISCONNECTS IF PANEL IS NOT IN EQUIPMENT ROOM.
|
|
> IF ELECTRICAL PANEL IS LOCATED IN EQUIPMENT ROOM,
|
|
> THEN THE PANEL MUST BE NEMA-4X RATED...
|
|
|
|
No panel schedule is provided.
|
|
|
|
SP400 Pool Equipment Room is not shown
|
|
on the Arch, Elec, Mech, or Plumbing sets.
|
|
It is not shown enclosed, even on the Spa set.
|
|
It seems like the Spa set was done last
|
|
with no coordination with other disciplines.
|
|
|
|
> With no other information
|
|
> I'd assume PVC, LFMC, and NEMA 4X disconnects
|
|
> to all equipment shown on SP400
|
|
> from the Garage panels.
|
|
|
|
Water Feature plans are a similar case.
|
|
|
|
> [!quote] [[joshua-komis]] 2026-05-28 around 10:30 (pp.)
|
|
> Assume a single-point connection
|
|
> to a pool equipment panel.
|
|
> 100A for the spa.
|
|
> Scope for equipment downstream of the panel
|
|
> should be excluded.
|
|
|
|
Neither [[jared-defanti]] nor I am satisfied with this answer.
|
|
This would mean excluding a significant number of connections.
|
|
|
|
Around 13:10 we spoke to [[joel-jansen]] about the issues.
|
|
He tended to agree with us
|
|
that the drawings suggested the EC would be responsible for more,
|
|
but said he would confirm with [[christian-pereiro]].
|
|
|
|
Christian directed us to respect Komis's direction.
|