# Wiring Method Selection
Determine where each wiring method can be used.
> [!important]
> This note covers general, system-agnostic selection.
> For certain specific applications,
> It may be necessary to deviate from the general case.
%% TODO
Scripts by others tend to beg questions of edge cases.
It's my intent that if a rule holds in _all_ cases,
even the super special one you're thinking I didn't consider,
that I specifically say so.
If I didn't say so, and your edge case is not covered,
you should seek clarification.
%%
## Example Wiring Method Selection
Below is an example Wiring Method Selection
for a [[ibc-construction-types#^5-over-1|podium]] construction.
> [!example]
> Wire Material:
> * Less than 100A: CU
> * 100A and larger: AL
>
> Outdoors:
> * Above-ground: EMT-Comp
> * Underground: PVC w/ Rigid Elbows
>
> Levels 1-2 (Type IA):
> * Concealed: MC
> * Exposed to Structure:
> * Up to 2"C: PVC In-Slab
> * 2-1/2"C and larger: EMT-SS OH
>
> Levels 3-5 (Type IIIA):
> * Concealed: NM/SER
> * Exposed to Structure: PVC OH
%%
This needs reworking.
I know PVC is preferable to MC in the case of feeders, subfeeds, and possibly home runs,
but I think they swap for branch.
%%
## Standard Indoor Wiring Methods
NM/SER < PVC in Slab < MC < EMT-SS < EMT-Comp
### NM/SER Overhead
Nonmetallic-sheathed cables are combustible,
so not permissible in Type [[ibc-construction-types#Type I Fire Resistive Non-Combustible|I]],
[[ibc-construction-types#Type II Non-Combustible|II]] constructions.
#### Concealment
Cable type wiring methods (MC, NM, SE)
may only be used where they will be concealed from view.
### PVC In-Slab
May require rigid stub-ups in certain cases,
which could make EMT more cost-effective.
Consult with the Senior Construction Estimator in this case.
> [!important]
> Be careful of ambiguous terminology in specifications and PDI proposals:
> "underground" and "below grade" are sometimes used inappropriately
> to describe PVC in-slab.
> It may be that rigid stub-ups are only necessary when emerging from grade (dirt),
> but not when emerging from the slab.
#### Garage Slab
_Conventional Slab_: PVC in Slab
_Precast_: EMT
See [[pdi-breakdowns#Garage]] for more info.
#### Slab Thickness
Conduits may only be routed through slabs of thickness
at least 3 times the outer diameter of the conduit.
| Conduit Size | Minimum Slab Thickness (in) |
| ------------:| ---------------------------:|
| 1/2" | 3.0 |
| 3/4" | 3.5 |
| 1" | 4.0 |
| 1-1/4" | 5.0 |
| 1-1/2" | 6.0 |
| 2" | 7.5 |
| 3" | 9.0 |
| 2-1/2" | 10.5 |
| 3-1/2" | 12.0 |
| 4" | 13.5 |
| 5" | 17.0 |
| 6" | 20.0 |
#### Shear Walls
[[construction-methods#Shear Walls|Shear Walls]]
Shear walls, like those around stairwells and elevator shafts,
may be routed through with special permission.
#### Post-Tensioned Slabs
[[construction-methods#Post-Tensioned Slab|Post-Tensioned Slab]]
> [!cite] [[joel-jansen]] 2025-08-15, in reference to [[belle-meade-plaza|Belle Meade Plaza]] (pp.)
> No affect on takeoff. Routing in slab still possible.
> [!cite] [[joel-jansen]] 2025-08-21, in reference to [[belle-meade-plaza|Belle Meade Plaza]] (pp.)
> PT slabs do have some affect on takeoff.
> 3in conduit can not be run in an 11in PT slab.
#### Pan Deck Slabs
[[construction-methods#Pan Deck Slab|Pan Deck Slab]]
> [!cite] [[joel-jansen]] 2025-08-15, in reference to [[belle-meade-plaza|Belle Meade Plaza]] (pp.)
> Do not route in slab.
### MC Cable Overhead
_Market Type = Assisted Living:_ MC-AP may be required.
#### Concealment
Cable type wiring methods (MC, NM, SE)
may only be used where they will be concealed from view.
> [!important] Exception:
> Temporary provisions for unfinished spaces
> (e.g. core and shell [[pdi-building-types#Retail|retail]])
#### Multi-Circuit Homeruns
Different schools of thought exist
on whether to use multi-neutral MC or EMT for homeruns.
Which is more cost-effective
is apparently subject to transient market conditions.
Seek clarification from your senior on a job by job basis.
> [!quote] Art Baldwin (pp.)
> Multi-circuit MC is not cost-effective
> when considering the difficulty of rework.
> Use conduit, even EMT if necessary.
### EMT Overhead
Set-screw fittings are cheaper than compression,
but may not be acceptable.
> [!info]
> EMT has a third coupling type "indenter",
> which are crimped onto the conduit using a special tool.
> These are usually only mentioned in specifications
> to say that they are unacceptable.
[[2025-10-15_09-32-00#Vanderbilt Central Neighborhood Residential College Spec Interpretation]]
## Standard Outdoor Wiring Methods
PVC Underground < EMT-Comp < IMC
### PVC Underground
May require rigid stub-ups.
### EMT Overhead
Use compression fittings.
## Nonstandard Indoor Wiring Methods
### PVC Overhead
Not usually permissible, except in Florida.
## By Specification
> [!info] Example Specs Relevant to Wiring Methods Selection
> * 26XXXX - Raceway And Boxes For Electrical Systems
> * 26XXXX - Conduits For Electrical Systems
> * 26XXXX - Underground Ducts And Raceways For Electrical Systems
>
> * 26XXXX - Low-Voltage Electrical Power Conductors And Cables
>
> * 26XXXX - General Requirements For Electrical
> * 26XXXX - Common Work Results For Electrical
## Flow Chart
```mermaid
flowchart
A[Construction Type]
A -- I, II --> B[Can be run in slab?]
B -- No --> D[Concealed?]
B -- Yes --> PVC
D -- No --> EMT
D -- Yes --> MC
A -- III, IV, V --> C[Concealed?]
C -- No --> PVC
C -- Yes --> NM/SER
```
#### Fire Rated Feeders
[[fire-resistive-wiring-methods-takeoff]]
PDI estimating practice is to run all "emergency" feeds
(life-safety or just standby)
in a 2-hour rated assembly.
This usually requires no change to takeoff for high-rises
since electrical riser rooms are themselves fire-rated.
* RHW-2 insulated conductors in conduit --- "Lifeline Cable"
* 2-hour rated metal clad cable --- "Vitalink"