| PDI Accubid Closeout: Quoted Material |
|
pdi-accubid-closeout |
PDI Accubid Closeout: Quoted Material
Important
Quoted material costs must be ==pre-tax==.
Fixtures
- Vendor <- "PDR - {Quote Type}" (e.g. "PDR - Spec/Equal", "PDR - VE")
- Quote <- Per PDI Systems proposal
- Notes <- Quote date
Tip
PDR fixture quotes are usually broken out by area type, buy it is not necessary to preserve this breakdown in the estimate. Use the sum total cost in a single Quoted Materials line item.
Switchgear
- Vendor <- Per quote (or "PDI BUDGET" if not available)
- Quote <- Per quote (or Bid Sheet Budget if not available)
- Notes <- Quote Date
Generator
- Vendor <- Per quote (or "PDI BUDGET" if not available)
- Quote <- Per quote (or Bid Sheet Budget if not available)
- Notes <- Quantity, Size in kW, Quote Date