# 2026-02-17 16:36:35
[[earned-value-management]]
is frequently stated to be capable of
"measuring project performance and progress
_in an objective manner_",[^1]
an analysis that is either optimistic
or totally misleading, depending on the context.
[^1]: [Wikipedia](https://en.wikipedia.org/wiki/Earned_value_management) (emphasis added)
EVM can be an objective measure of _progress_,
but measuring _performance_,
variance of actual cost/hours versus estimated,
(obviously) requires an estimate,
which is subject to bias and error.