# Estimating Methodologies
|
|
|
|
## The 4 Traditional Methodologies
|
|
|
|
> [!quote] Defense Acquisition University
|
|
> There are four principal cost estimating methodologies:
|
|
> 1. Comparison/analogy,
|
|
> 2. Parametric,
|
|
> 3. Detailed engineering/bottom up, and
|
|
> 4. Extrapolation from actual costs.
|
|
|
|
### Comparison / Analogy
|
|
|
|
**Pros:**
|
|
* simple to implement
|
|
* quick in practice
|
|
|
|
**Cons:**
|
|
* unsatisfying input
|
|
* unsatisfying output
|
|
|
|
### Parametric
|
|
|
|
**Pros:**
|
|
* quick in practice
|
|
* nuanced input
|
|
* accounts for incomplete input
|
|
* effectively accurate through the entire estimate process
|
|
* well-suited for automation
|
|
|
|
**Cons:**
|
|
* complex to implement
|
|
|
|
### Detailed Engineering / "Bottom-Up"
|
|
|
|
**Pros:**
|
|
* simple to implement
|
|
* satisfying output
|
|
|
|
**Cons:**
|
|
* slow in practice
|
|
* unsatisfying input
|
|
* accuracy and risk depend solely on estimator
|
|
* output dependent on complete input
|
|
* ill-suited to automation
|
|
|
|
### Extrapolation from Actual Costs
|
|
|
|
Depending on the application this is one is either
|
|
* better described as the previous 3
|
|
* or not estimating at all.
|
|
|
|
## In Other Industries
|
|
|
|
There exist articles from software development project management resources
|
|
stating essentially what I believe to be true,
|
|
that parametric estimating is _more_ accurate than bottom-up,
|
|
in contrast to common assumption.
|
|
|
|
I suspect that industry tolerance for cost-modeling
|
|
is related to the cost of estimation.
|
|
Software is largely impractical to estimate bottom-up,
|
|
whereas anyone can take off construction scope.
|
|
|
|
Alternate theory:
|
|
tolerance is related to the industry's ability to understand the model.
|
|
|
|
Regardless, a continuum emerges:
|
|
|
|
```
|
|
^
|
|
| Software
|
|
| Defense
|
|
| Construction
|
|
v
|
|
```
|
|
|
|
Industries that would benefit the most from cost-modeling
|
|
are least likely to consider it a valid method.
|
|
|
|
These methods are actually the same, just different levels of abstraction.
|
|
This can be observed in the _very_ subtle distinction
|
|
between parametric and analogous estimating,
|
|
which also exists in my history-oriented/risk-oriented definitions.
|
|
|
|
```
|
|
# of Parameters
|
|
^
|
|
| Bottom-Up (100+)
|
|
| Parametric (10)
|
|
| Analogous (1)
|
|
| Extrapolation (0)
|
|
```
|
|
|
|
These different methods are just a response
|
|
to different levels of requirement specificity.
|
|
Parametric is obviously more accurate and precise than analogous,
|
|
however the question not being asked
|
|
is if there are diminishing returns to estimate specificity.
|
|
|
|
Suppose there are, at some point then,
|
|
there must then be a point at which **risk of human error**
|
|
outweighs the value of more perfect information.
|