# Feeders
|
|
|
|
## Info
|
|
|
|
### Routing and Structural Considerations
|
|
|
|
#### Shear Walls
|
|
|
|
Shear walls, like those around stairwells and elevator shafts,
|
|
may be routed through with special permission.
|
|
|
|
#### Post-Tensioned Slabs
|
|
|
|
> [!example]
|
|
> STRUCTURAL SLAB IS AN 8-INCH THICK
|
|
> UNBONDED POST-TENSIONED TWO-WAY SLAB UNLESS NOTED OTHERWISE.
|
|
|
|
> [!cite] Joel Jansen 2025-08-15, in reference to Belle Meade Plaza (pp.)
|
|
> No affect on takeoff. Routing in slab still possible.
|
|
|
|
> [!cite] Joel Jansen 2025-08-21, in reference to Belle Meade Plaza (pp.)
|
|
> PT slabs do have some affect on takeoff.
|
|
> 3in conduit can not be run in an 11in PT slab.
|
|
|
|
#### Pan Deck Slabs
|
|
|
|
> [!example]
|
|
> STRUCTURAL SLAB IS 3 1/2 INCHES OF NORMALWEIGHT CONCRETE
|
|
> ON 3-INCH COMPOSITE STEEL DECK UNLESS NOTED OTHERWISE.
|
|
|
|
> [!cite] Joel Jansen 2025-08-15, in reference to Belle Meade Plaza (pp.)
|
|
> Do not route in slab.
|
|
|
|
#### Fire Rated Feeders
|
|
|
|
PDI estimating practice is to run all "emergency" feeds
|
|
(life-safety or just standby)
|
|
in a 2-hour rated assembly.
|
|
This usually requires no change to takeoff for high-rises
|
|
since electrical riser rooms are themselves fire-rated.
|
|
|
|
* RHW-2 insulated conductors in conduit -- "Lifeline Cable"
|
|
* 2-hour rated metal clad cable -- "Vitalink"
|
|
|
|
### Formatting
|
|
|
|
All feeder takeoff descriptions should be prefixed with `<parent> TO <child>`
|
|
|
|
> [!cite] Joel Jansen, in reference to Omni Hotels Raleigh, pp.
|
|
> It is acceptable to use typicals for identical feeders
|
|
> (i.e. meter centers fed from bus plugs)
|
|
> so long as the typical is in the Feeders `Area`.
|
|
|
|
## Sequence
|
|
|
|
### 1. Estimate preparation
|
|
|
|
Read about the project specifications and construction type:
|
|
* Deck thickness
|
|
* Wiring methods
|
|
* Conductor material
|
|
* Wire terminations (set-screw acceptable or compression required?)
|
|
|
|
Locate:
|
|
* Riser Diagram
|
|
* Feeder Schedule (if present)
|
|
* Main Electrical rooms and panel locations
|
|
|
|
### 2. Takeoff
|
|
|
|
Run parallel to building lines
|
|
and route through corridors where possible.
|
|
|
|
> [!important]
|
|
> All takeoffs in Systems with names including "site"
|
|
> should be in "Site" Area, Phase, and Bid Item breakdowns.
|
|
|
|
For adjacent panels, use a minimum 10ft length.
|
|
|
|
#### Adders
|
|
|
|
Use the difference in elevation between equipment
|
|
or 10ft, whichever is greater.
|
|
|
|
Add an additional 5ft (total 15ft) for site runs
|
|
(primaries, secondaries, etc.).
|
|
|
|
#### Primaries
|
|
|
|
Usually only empty conduit if included.
|
|
|
|
#### Secondaries
|
|
|
|
##### Wiring on Vault Racks
|
|
|
|
Where secondary conductors run on racks in utility vaults
|
|
manually set the length of conduit,
|
|
measure the wire length,
|
|
add 20ft in addition to previously mentioned adders.
|
|
|
|
#### Feeders
|
|
|
|
`Area` = "01 - Feeders/Risers Building"
|
|
for all feeders, no matter the location.
|
|
|
|
#### Bus Duct
|
|
|
|
`COMMON ASSEMBLIES`/`DISTRIBUTION`/`BUS DUCT`
|
|
|
|
#### Cable Support
|
|
|
|
> [!quote] 300.19 Supporting Conductors in Vertical Raceways.
|
|
> **(A) Spacing Intervals -- Maximum.**
|
|
> Conductors in vertical raceways shall be supported
|
|
> if the vertical rise exceeds the values in Table 300.19(A).
|
|
> At least one support method shall be provided for each conductor
|
|
> at the top of the vertical raceway or as close to the top as practical.
|
|
> Intermediate supports shall be provided
|
|
> as necessary to limit supported conductor lengths
|
|
> to not greater than those values specified in Table 300.19(A).
|
|
|
|
> [!cite] Table 300.19(A) Spacings for Conductor Supports
|
|
>
|
|
> | Conductor Size | Aluminum or Copper-Clad Aluminum | Copper |
|
|
> | -------------------------------- | --------------------------------:| ------:|
|
|
> | 18 AWG through 8 AWG | 100ft | 100ft |
|
|
> | 6 AWG through 1/0 AWG | 200ft | 100ft |
|
|
> | 2/0 AWG through 4/0 AWG | 180ft | 80ft |
|
|
> | Over 4/0 AWG through 350 kcmil | 135ft | 60ft |
|
|
> | Over 350 kcmil through 500 kcmil | 120ft | 50ft |
|
|
> | Over 500 kcmil through 750 kcmil | 95ft | 40ft |
|
|
> | Over 750 kcmil | 85ft | 35ft |
|
|
|
|
`ITEM DATABASE`/`CONDUIT & FITTINGS`/`CABLE SUPPORT / WEDGES`/`... COMPLETE FITTING`/...
|
|
|
|
#### Grounding
|
|
|
|
See [[grounding]].
|
|
|
|
#### Sleeving
|
|
|
|
See [[sleeving]].
|
|
|
|
### 3. Extension (Review and Checking)
|