title: ConEst Pre-Takeoff Email Template
|
|
tags:
|
|
- authorship/other
|
|
- occupational
|
|
- type/media
|
|
- exclude-from-word-count
|
|
up: "[[pdi-pre-takeoff-confirmation]]"
|
|
---
|
|
# ConEst Pre-Takeoff Email Template
|
|
|
|
%%
|
|
Email template for use in [[pdi-pre-takeoff-confirmation]].
|
|
|
|
This template effectively replicates the official template
|
|
originally written in Microsoft Word.
|
|
|
|
It's my belief that this template can not be implemented
|
|
without significant modifications specific to the intended project.
|
|
See implementations elsewhere in this notebook for reference.
|
|
%%
|
|
|
|
Hello Team,
|
|
|
|
Below is a comprehensive list of means & methods for {Project Name}.
|
|
Please confirm you have received this email and respond with any questions or comments.
|
|
|
|
* **Delivery Method:** %% Plans & Specs, Design Build, Design Assist, P&S with Approved VE %%
|
|
* **Document Stage:** %% DD, CD, Permit, GMP, Bid, Awarded %%
|
|
* **Drawings Date:** %% Date %%
|
|
* **Project Manual Date:** %% Date %%
|
|
* **Proposal Date:** %% Date %%
|
|
* **Takeoff Request Stage:** %% Stage 1, Full takeoff, etc. %%
|
|
|
|
### Project Specification Callouts
|
|
|
|
%% Put page of Drawing or PM after answer %%
|
|
|
|
* Conduit Execution Plans:
|
|
%% GRC, coupling specs, etc. %%
|
|
* Wire:
|
|
%% Copper or Aluminum, Acceptable Manufacturers %%
|
|
* Cable Uses:
|
|
%% Branch Homeruns %%
|
|
* Steel Box Depth:
|
|
%% 1-1/2", 2-1/8" %%
|
|
* Floor Boxes:
|
|
* Box Material:
|
|
%% Box: PVC, Sheet metal, Cast iron %%
|
|
* Cover Material:
|
|
%% Covers: Brass, Aluminum %%
|
|
* Wiring Devices:
|
|
* Units:
|
|
%% 15A Decora %%
|
|
* BOH/Common Areas:
|
|
%% 20A Toggle %%
|
|
* Switchboards/Panelboards:
|
|
%% Acceptable Manufacturers, AL or CU Bussing, Breaker Types (Snap-on, bolt on), ACI Ratings %%
|
|
* Transformers:
|
|
%% Windings AL or CU, K-rating %%
|
|
* Generator:
|
|
%% Acceptable manufacturers, Enclosure Specs, Sound Rating, Remote Tank, Tank Size, Load Banks %%
|
|
|
|
### Project Drawing/Detail Callouts
|
|
|
|
* Describe conflicts between drawings / proposal:
|
|
%% "Plans show CU feeders, proposal calls for aluminum", Specification grade devices, etc. %%
|
|
|
|
* Cost drivers in details not shown elsewhere on plans:
|
|
|
|
### PDI System Execution Plan
|
|
|
|
* Primaries:
|
|
%% Installation only, (9) 6" PVC %%
|
|
* Secondaries:
|
|
%% PVC UG, GRC Stub-ups, AL %%
|
|
* Feeders:
|
|
%% PVC UG, EMT OH, AL over 100A, 2% VD %%
|
|
* Unit Subfeeds:
|
|
%% MC OH AL, VD per Chart on E5.01 %%
|
|
* Units:
|
|
%% 15A Decora, Insinkerators, T-stat, Floor Boxes, Shade Control, Doorbells, Dimmer Switches, etc. %%
|
|
* Telecom:
|
|
%% 42" MSDE, No Cable Homeruns, (1) 1" Back to IDF, CAT6 with Stub-ups %%
|
|
* EV Chargers:
|
|
%% 42) Conduit only, (56) Conduit & Wire, (20) Conduit, Wire & Equipment %%
|
|
* Fire Alarm:
|
|
%% Free-air where allowed by code. EMT Risers. %%
|
|
* DAS:
|
|
%% Conduit only, Per PDI DAS Design %%
|
|
* Low Voltage:
|
|
%% Free-air where allowed by code. Stub-ups to accessible ceilings. %%
|
|
|
|
### Lighting Control
|
|
|
|
* Scope:
|
|
%% Code Minimum per Energy Code Assigned, P&S, PDI Design %%
|
|
|
|
* Area: %% Assign Method to Areas: Line Voltage, Low-Voltage Stand Alone or Centralized System %%
|
|
* BOH:
|
|
* Corridor:
|
|
* Amenity:
|
|
* Site/Landscape:
|
|
* Garage Entry Point
|
|
* Office:
|
|
|
|
### Tasks/Quotes Needed for WBS
|
|
|
|
<!--
|
|
Delete any tasks completed.
|
|
If all necessary tasks are open or completed:
|
|
"No tasks missing."
|
|
-->
|
|
|
|
* Electrical Constructability Review
|
|
* Electrical VDC
|
|
* Coordination Study %% _Design Build:_ Not needed. %%
|
|
* DAS Public Safety Raceway Design
|
|
|
|
<!--
|
|
DAS Public Safety Raceway Design is necessary
|
|
if we own DAS pathways but not the system,
|
|
since if we own the system,
|
|
the raceway design will be included in the Systems quote.
|
|
-->
|
|
|
|
Thank you,
|