title: Telecom Takeoff
|
|
tags:
|
|
- occupational/takeoff
|
|
- status/draft
|
|
- type/guide
|
|
up: "[[takeoff-scripts]]"
|
|
aliases:
|
|
- telecom takeoff
|
|
---
|
|
# Telecom Takeoff
|
|
|
|
> [!info] Scope
|
|
> * Telephone
|
|
> * Data
|
|
> * Cable TV
|
|
|
|
> [!important]
|
|
> Not to be confused with [[low-voltage-takeoff]].
|
|
|
|
## Note: Empty Conduit
|
|
|
|
Where `COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
|
|
is specified, `FEEDER CONDUIT AND WIRE`/...
|
|
is also acceptable.
|
|
|
|
## Site Low Voltage Duct Bank
|
|
|
|
1. * `Area` = "2 - Site"
|
|
* `Phase` = "Site"
|
|
* `System` = "LVD - Site Low Voltage Ductbank"
|
|
* `Bid Item` = "1 - Site"
|
|
|
|
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
|
|
* Size and quantity per proposal > drawings > assume (4) 4"C
|
|
* **Length** = Length measured from MDF to 5ft beyond building footprint
|
|
|
|
_Garden Style:_ Outside of every building
|
|
|
|
> [!important] Long-Radius Elbows
|
|
> Note requirements for long-radius elbows,
|
|
> substitute items as necessary.
|
|
|
|
### Telecom Vaults
|
|
|
|
"Quazite Box"
|
|
polymer concrete enclosure
|
|
|
|
1. `TEMPORARY ITEMS`/`Quazite Box ...`
|
|
* **Material Price** = 1000.00
|
|
* **Labor Hours** = 12.00
|
|
* **Sort Code ?** = 200
|
|
|
|
Alternative
|
|
|
|
1. `COMMON ASSEMBLIES`/`POLES / EXCAVATION / CORING / UG PULL BX`/`MANHOLES / PULL BOXES / EXCAVATION / CONCRETE`/`QUAZITE UG PULL BOXES`/...
|
|
|
|
## Backbone Riser
|
|
|
|
* `Phase` = "Building - BOH ..."
|
|
* `System` = "TC - Telecom Backbone"
|
|
|
|
If not shown:
|
|
* _Garden Style:_ (2) 4"C
|
|
* _High Rise, Mid Rise:_ (4) 4"C
|
|
|
|
### Horizontal Backbone
|
|
|
|
1. * `Drawing` = Telecom riser diagram
|
|
* `Area` = Area of riser room
|
|
|
|
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
|
|
* **Length** = Length measured from MDF to IDF
|
|
* Input adder length to reach the level of the IDF (Minimum 15ft).
|
|
|
|
### Vertical Backbone
|
|
|
|
1. * `Drawing` = Telecom riser diagram
|
|
* `Area` = "Typical - Building All Levels"
|
|
|
|
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
|
|
* Delete elbows if unnecessary.
|
|
* **Length** = Height between floors (Minimum 15ft)
|
|
|
|
## Telecom Backboards
|
|
|
|
As shown on plans,
|
|
only if not excluded in proposal.
|
|
|
|
1. * `Phase` = "Building - BOH ..."
|
|
* `System` = "TC - Telecom Backbone"
|
|
|
|
`COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`... PLYWOOD BACKBOARD`
|
|
* **Count** = As shown
|
|
|
|
## Corridor Conduit (IDF to Unit MSDE)
|
|
|
|
One Takeoff per Area per level
|
|
|
|
1. `COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
|
|
* **Length** = Average of subfeed lengths * # of Units
|
|
* **Count** = # of Units
|
|
|
|
[[2026-05-04_14-57-49]]
|
|
## Inner Duct
|
|
|
|
For future use (e.g. fiber)
|
|
|
|
1. `TEMPORARY ITEMS`/`MaxCell 3" 3 Cell`
|
|
* **Material Price** = 450.00/C
|
|
* **Labor Hours** = 12.00/C
|
|
|
|
_Alternative:_
|
|
|
|
1. `COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/`INNERDUCT`/`... (GP)`
|
|
|
|
## Devices
|
|
|
|
As shown on plans.
|
|
Ignore scope shared with [[electrical-takeoff|electrical]]
|
|
(e.g. floor boxes).
|
|
|
|
1. `COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/...
|
|
* .../`BOH / AMENITY ASSEMBLIES`
|
|
* .../`SCREWLESS DECORA COVERS UNITS / BOH`
|
|
* .../`ROUGH IN ASSY`
|
|
|
|
If _system_ is included,
|
|
take off _both_ rough-in and device assemblies
|
|
in amenity areas.
|
|
|
|
If rough-in is included,
|
|
always provide backboxes and conduit stub-ups for outlets in other than units,
|
|
even if qualified as "free-air per code" or similar.[^1]
|
|
|
|
[^1]: [[2026-03-25_08-14-59#"Free-Air Per Code"]]
|