# Lighting Controls Takeoff
|
|
|
|
> [!info]
|
|
> See [[lighting-controls]] for more on lighting controls systems.
|
|
|
|
> [!info] "Local Control" as a PDI proposal qualification
|
|
> The term "local control only" is sometimes used to indicate
|
|
> no consideration for _any_ lighting control beyond standard devices,
|
|
> (with `$D`'s being the triac type)
|
|
> however, this phrasing is ambiguous and non-universal.
|
|
> Confirm with [[pdi-estimating#Bid Estimating|bid team]] on what must be included.
|
|
|
|
Determine which Systems and Codes are required:
|
|
* _IBC/IECC 2021 or later:_ all fixtures 0-10V dimmable.
|
|
|
|
## PDI Lighting Control Configurations
|
|
|
|
### Stand Alone
|
|
|
|
0-10V dim -- "LV cable" is 2 conductor
|
|
|
|
Takeoff rough-in for switches and occupancy sensors
|
|
* **Branch Length** = length of room
|
|
|
|
Takeoff the lighting control relay (DLM)
|
|
|
|
Takeoff an additional controller if receptacles are controlled
|
|
|
|
Takeoff homeruns to the DLM (one per controlled circuit)
|
|
* Note: Not necessarily per room, several rooms may share a lighting circuit.
|
|
|
|
### Networked
|
|
|
|
#### Devices
|
|
|
|
##### Room Controllers
|
|
|
|
No room controllers are necessary,
|
|
lighting zones are switched from a central lighting control panel (LCP)
|
|
|
|
##### Switches and Sensors
|
|
|
|
Takeoff rough-in for switches and occupancy sensors
|
|
|
|
??
|
|
(only if time based; length based on closeness to sw/occ sensor)
|
|
??
|
|
|
|
#### Homeruns
|
|
|
|
Takeoff 1 circuit homerun per lighting zone.
|
|
|
|
### Wattstopper
|
|
|
|
PDI default configuration
|
|
|
|
Takeoff (1) DLM controller for the fixtures
|
|
and (1) Plug controller for the receptacle
|
|
* If room has both dimmable fixtures and the controlled receptacle,
|
|
only (1) DLM controller and (1) Plug controller
|
|
* Use MC to cover room if drop
|
|
* Use EMT if exposed or MC not permitted
|
|
|
|
Takeoff normal power to the controlled load
|
|
* Add LV cable to fixture branch
|
|
* Use 12/3 for receptacles
|
|
|
|
Takeoff rough-in for both the occ sensors and the LV switch
|
|
* Free air if possible
|
|
* **Length** = length of room
|
|
|
|
Cat cabling from the controllers on is likely provided by systems
|
|
* Confirm with chief or quote language
|
|
|
|
#### Corridor Occupancy Sensors
|
|
|
|
If occupancy sensors are shown in the corridors:
|
|
|
|
Takeoff homerun back to the electric room
|
|
|
|
Takeoff (1) DLM controller for each electric room
|
|
* Run free air down corridor
|
|
|
|
Takeoff rough-in for each occupancy sensor shown.
|
|
|
|
#### Network Bridge
|
|
|
|
Check systems quote to determine if network bridges are needed.
|
|
|
|
Takeoff (1) back box for every ==group of rooms you want together==
|
|
|
|
??
|
|
If not showing, put one in every room with a controller
|
|
??
|
|
|
|
#### Homeruns
|
|
|
|
Need a HR into the room for the controllers
|
|
* Can link multiple controllers (aka rooms) together if you have the same circuit
|
|
* Go back to closest electric room
|
|
|
|
## Custom Switch Boxes
|
|
|
|
For switch combinations not in `COMMON ASSEMBLIES`,
|
|
create [[heating-designations]] based on the most similar.
|