## Info
|
|
|
|
### Special Equipment
|
|
|
|
#### Company Switches
|
|
|
|
> [!info] Also Known As
|
|
> * Theatrical Switchboards
|
|
> * Stage Switchboards
|
|
|
|
Company switches are lighting control devices
|
|
unique to performance venues
|
|
like those subject to **NEC Article 520:
|
|
Theaters, Audience Areas of Motion Picture and Television Studios,
|
|
Performance Areas, and Similar Locations**
|
|
|
|
![[company-switch.png|500x625]]
|
|
|
|
> [!cite] NEC Article 520.2
|
|
> **Stage Switchboard.**
|
|
> A permanently installed switchboard, panelboard, or rack
|
|
> containing dimmers or relays with associated overcurrent protective devices,
|
|
> or overcurrent protective devices alone, used primarily to feed stage equipment.
|
|
|
|
## Sequence
|
|
|
|
### 1. Preparation
|
|
|
|
1. Initial the OneNote
|
|
2. In the drawings, locate:
|
|
* Riser Diagrams
|
|
* House Panels
|
|
|
|
### 2. Takeoff
|
|
|
|
1. Build Items in Distribution:
|
|
* Panelboards
|
|
* Switchboards
|
|
* Meter centers
|
|
* Generators
|
|
* Transfer switches
|
|
* Generator connection cabinets
|
|
* CT cabinet
|
|
* Power monitor
|
|
|
|
2. Takeoff Common Assemblies:
|
|
* XFMRs
|
|
* Disconnect switches
|
|
|
|
3. Takeoff Items in Item Database:
|
|
* Wireway (Trough/Gutter)
|
|
|
|
4. Takeoff Temp Assemblies:
|
|
* Fire Pump
|
|
* Fire Pump Controller
|
|
|
|
When building panelboards/switchboards,
|
|
add terminations according to an example from the schedules.
|
|
**Do not include feeder terminations.**
|
|
|
|
Items to Avoid:
|
|
* Tap Boxes
|
|
* Bus Duct
|
|
* Vault Room
|
|
* Anything FPL
|
|
* Grounding
|
|
* Elevator Room
|
|
|
|
#### SPD's/TVSS's
|
|
|
|
Labor only.
|
|
|
|
Specific item is not important, but I use
|
|
`SPLITTERS / SOCKETS / CABINETS`/`METER SOCKETS & CABINETS`/`METERING CURRENT TRANSFORMER`
|
|
(Labor = 1.5hrs)
|
|
for consistency.
|
|
|
|
#### Submeters/Power Monitors
|
|
|
|
See [[switchgear#SPD's/TVSS's]]
|
|
|
|
#### Panelboards
|
|
|
|
`DISTRIBUTION`/`DIST PANELS & UNIT LOAD CENTERS`/...
|
|
|
|
#### Enclosed Circuit Breakers
|
|
|
|
Treat as disconnect switch.
|
|
|
|
#### Generators
|
|
|
|
Add `DISTRIBUTION FITTINGS`/`GENERATOR SET UP`.
|
|
|
|
#### Generator Connection Cabinets
|
|
|
|
Use a Distribution Panel of equal amps.
|
|
|
|
#### Transfer Switches
|
|
|
|
> "300A ATS"
|
|
|
|
##### Transfer Switches 1200A+
|
|
|
|
Use 1200A MTS/ATS, and add:
|
|
|
|
* ==CA.33.14.AMPS==
|
|
* Factor 1 = 3
|
|
* ==Delete 1200A==
|
|
|
|
#### Meter Centers
|
|
|
|
`SWITCHGEAR & METER CENTERS`/`METER CENTERS`/`... METERING SECTION`
|
|
|
|
Adjust Factor 1 for meter stacks, delete zeroed items.
|
|
|
|
### 3. Review
|
|
|
|
1. Generator
|
|
* Ensure takeoff is in the generator Area and System breakdowns
|
|
* Put location, quantity, and type on OneNote
|