Pre-Takeoff Confirmation --- Charlotte South End Hotel

%% Implementation of conest-pre-takeoff-email-template for charlotte-south-end-hotel %%

Hello Team,

Below is a comprehensive list of means & methods for Charlotte South End Hotel. Please confirm you have received this email and respond with any questions or comments.

  • Delivery Method: Plans & Specs
  • Document Stage: Issue for Permit
  • Drawings Date: 2026-02-27
  • Project Manual Date: 2026-02-27
  • Proposal Date: 2025-12-12
  • Takeoff Request Stage: Full Takeoff

Project Specification Callouts

  • Conduit:

    • EMT Fittings: ---Spec 260510 2.4(N)(2) (p. 2226)
      • Smaller than trade size 2-1/2": Compression
      • Trade size 2-1/2" and larger: Set-screw
  • Wire:

    • Material: Aluminum 1 AWG and larger ---Spec 260510 2.2(C)(1) (p. 2224)
    • Acceptable Manufacturers: ---Spec 260510 2.2(D) (p. 2224)
      • Encore Wire
      • General Cable
      • Okonite
      • Paranite
      • Pirelli
      • Senator
      • Southwire
  • MC Cable:

    • Application: "dry locations only where approved by code authority." ---Spec 260510 2.4(N)(8) (p. 2227)

    • Acceptable Manufacturers: ---Spec 260510 2.2(E) (p. 2224)

      • Alflex
      • AFC
      • America Metal Moulding
      • Encore Wire
      • Southwire
  • Steel Box Depth: Not specified ---Spec 260510 2.12(A) (p. 2231)

  • Floor Boxes: ---Spec 260510 2.12(E) (p. 2231)

    • Box Material:

      • Slab on grade: Cast iron
      • Slabs above grade: Stamped steel
    • Cover Material: Not specified.

  • Wiring Devices:

    • All Areas:
      • Current rating: 20A ---Spec 260510 2.16(B)(1) (p. 2231)
      • Standard/Decora: Decora ---Spec 260510 2.16(D) (p. 2231)
  • Switchboards:

    • Bus Material: "aluminum or copper, tin or silver plated" ---Spec 262000 2.6(C)(4) (p. 2297)
    • OCPD Interrupting Current Ratings: Not specified.
    • Acceptable Manufacturers: ---Spec 262000 2.17(C) (p. 2307)
      • Eaton
      • ABB/GE
      • Schneider Electric
      • Siemens
  • Panelboards:

    • Bus Material: "silver plated copper or electro-tin plated aluminum" ---Spec 262000 2.8(E) (p. 2303)

    • Breaker Types: Bolt-on ---Spec 262000 2.9(C) (p. 2303)

    • OCPD Interrupting Current Ratings:

      • Distribution Panelboards: Not specified.
      • Lighting and Appliance Panelboards: Not less than 10kAIC ---Spec 262000 2.10(A)(3) (p. 2304)
    • Acceptable Manufacturers: ---Spec 262000 2.17(C) (p. 2307)

      • Eaton
      • ABB/GE
      • Schneider Electric
      • Siemens
  • Transformers:

    • Winding Material: "Transformer windings shall be manufacturer's standard design, copper or aluminum conductor. Bussing shall be copper." ---Spec 262002.5(L) (p. 2296)

    • K-Rating: Only as shown (None shown) ---Spec 262002.5(K) (p. 2295)

    • Acceptable Manufacturers: ---Spec 262000 2.17(D) (p. 2307)

      • Eaton
      • ABB/GE
      • Heavy Duty
      • MGM
      • Siemens
      • Schneider Electric
      • United Power Corp
  • Generator: (1) 500kW Diesel ---Dwg. E05-12

    • Enclosure Specs: Not specified.
    • Remote Tank: None shown or specified.
    • Tank Size: 12hrs at full load ---Spec 263213 2.7(C) (p. 2326)
    • Load Banks: None shown or specified.
    • Acceptable Manufacturers: ---Spec 263213 2.1(A) (p. 2323)
      • Caterpillar Tractor Co.
      • Cummins/Power Generation
      • Kohler Power Systems (MTU Engine Only)
      • MTU On-Site Energy

Project Drawing/Detail Callouts

  • Describe conflicts between drawings / proposal: %% "Plans show CU feeders, proposal calls for aluminum", Specification grade devices, etc. %%

  • Cost drivers in details not shown elsewhere on plans:

PDI System Execution Plan

  • Primaries: Conduit only; wiring, duct bank by others.

  • Secondaries: Aluminum bus duct. ---Spec 262000 2.11(D) (p. 2305) %% PVC UG, GRC Stub-ups, AL %%

  • Feeders: PVC UG, EMT OH. Size and material per E05-10 schedule (AL 100A and larger, ==transformer primaries and secondaries all copper==). Voltage drop not considered (allowance per E00-00, "GENERAL PRICING NOTES"). %% PVC UG, EMT OH, AL over 100A, 2% VD %% %% Emergency Feeds MI Cable %%

  • Unit Subfeeds: #12 Multi-Circuit MC OH. Voltage drop not considered (allowance per E00-00, "GENERAL PRICING NOTES"). %% MC OH AL, VD per Chart on E5.01 %% %% 2026-03-10_13-51-32#Voltage Drop %%

  • Units:

    • VFCU HVAC
    • 20A Decora Switches
    • 20A Decora Receptacles
    • Master Switch control
    • Floor boxes (0--1 per K, QQ unit; 2 per 2B, 3B unit) %% 15A Decora, Disposals, T-stat, Floor Boxes, Shade Control, Doorbells, Dimmer Switches, etc. %%
  • Telecom: Rough-in only, system alternate. Free-air where allowed by code. EMT Risers.

  • EV Chargers: Excluded (alternate). %% (42) Conduit only, (56) Conduit & Wire, (20) Conduit, Wire & Equipment %% %% 2026-03-10_13-51-32#EV Chargers %%

  • Fire Alarm: Free-air where allowed by code. EMT Risers.

  • DAS: Rough-in only, per PDI DAS Design.

  • Low Voltage: Free-air where allowed by code. Stub-ups to accessible ceilings. ---Proposal 2025-12-12 Ex. B Notes

Lighting Control

%% 2026-03-10_13-51-32#Lighting Control %%

  • Applicable Code: 2024 North Carolina Energy Conservation Code (2021 IECC with NC Amendments) ---Dwg. G00-11

  • Basis of Takeoff: Central dimming system per P&S, PDR quote.

  • By Area:

    • Units: Master Switch, Digital Standalone Control, 0-10V dimming.
    • Amenity: Digital Central Control, 0-10V dimming.
    • Corridors: 0-10V dimming per 2021 IECC and LEED checklist.
    • BOH: Line voltage control.
    • Garage: Line voltage control (integral dimming occupancy sensors). %% Assign Method to Areas: Line Voltage, Low-Voltage Stand Alone or Centralized System %%

Tasks/Quotes Needed for WBS

%% Only tasks that are not already open. %%

  • DAS Public Safety Raceway Design %% Necessary because we own DAS pathways but not the system %%

%%

  • Electrical Constructability Review
  • Electrical VDC
  • Coordination Study %%

Thank you,