@@ -19,22 +19,22 @@ title: Telecom
> [!important]
> Not to be confused with [[low-voltage-takeoff]].
## Note: Empty Conduit
Where `COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
is specified, `FEEDER CONDUIT AND WIRE`/...
is also acceptable.
## "Site Low Voltage Duct Bank"
* Conduit from outside of building to MDF
1. * `Area` = "2 - Site"
* `Phase` = "Site"
* `System` = "LVD - Site Low Voltage Ductbank"
* `Bid Item` = "1 - Site"
| | |
| ---------- | --------------------------------- |
| `Area` | "2 - Site" |
| `Phase` | "Site" |
| `System` | "LVD - Site Low Voltage Ductbank" |
| `Bid Item` | "1 - Site" |
`COMMON ASSEMBLIES`/`PDI EMPTY CONDUIT`
Size and quantity per proposal > drawings > assume (4) 4"C
* **Length** = Length measured from MDF to 5ft beyond building footprint
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
* Size and quantity per proposal > drawings > assume (4) 4"C
* **Length** = Length measured from MDF to 5ft beyond building footprint
_Garden Style:_ Outside of every building
@@ -47,80 +47,78 @@ _Garden Style:_ Outside of every building
"Quazite Box"
polymer concrete enclosure
`TEMPORARY ITEMS`/...
1. `TEMPORARY ITEMS`/`Quazite Box ...`
* **Material Price** = 1000.00
* **Labor Hours** = 12.00
* **Sort Code ?** = 200
* **Material Price** = 1000.00
* **Labor Hours** = 12.00
* **Sort Code**? = 200
Alternative
`COMMON ASSEMBLIES`/`POLES / EXCAVATION / CORING / UG PULL BX`/`MANHOLES / PULL BOXES / EXCAVATION / CONCRETE`/...
1. `COMMON ASSEMBLIES`/`POLES / EXCAVATION / CORING / UG PULL BX`/`MANHOLES / PULL BOXES / EXCAVATION / CONCRETE`/...
## Backbone Riser
* `Phase` = "Building - BOH ..."
* `System` = "TC - Telecom Backbone"
(2) 4"C or (4) 4"C ULO
| | |
| --------- | ------------------------------- |
| `Phase` | "Building - BOH ..." |
| `System` | "TC - Telecom Backbone" |
Add sleeves
### Horizontal Backbone
| | |
| --------- | --------------------- |
| `Drawing` | Telecom riser diagram |
| `Area` | Area of riser room |
1. * `Drawing` = Telecom riser diagram
* `Area` = Area of riser room
* **Length** = Length measured from MDF to IDF.
* Input adder length to reach the level of the IDF (Minimum 15ft).
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
* **Length** = Length measured from MDF to IDF
* Input adder length to reach the level of the IDF (Minimum 15ft).
### Vertical Backbone
| | |
| --------- | ------------------------------- |
| `Drawing` | Telecom riser diagram |
| `Area` | "Typical - Building All Levels" |
1. * `Drawing` = Telecom riser diagram
* `Area` = "Typical - Building All Levels"
* **Length** = Length between floors (15ft ULO)
`COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
* Delete elbows if unnecessary.
* **Length** = Height between floors (Minimum 15ft)
## Telecom Backboard
As shown on plans.
As shown on plans, only if not excluded in pro
| | |
| -------- | ------------------------------- |
| `Phase` | "Building - BOH ..." |
| `System` | "TC - Telecom Backbone" |
1. * `Phase` = "Building - BOH ..."
* `System` = "TC - Telecom Backbone"
`COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`... PLYWOOD BACKBOARD`
`COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`... PLYWOOD BACKBOARD`
* **Count** = As shown
## Corridor Conduit (Unit MSDE to IDF)
Empty conduit, either of
* `FEEDER CONDUIT AND WIRE`/...
* `COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
One Takeoff per Area per level
* **Length** = Average of subfeed lengths × # of Units
* **Count** = # of Units
1. `COMMON ASSEMBLIES`/`PDI EMPTY & DUCTBANK CONDUIT`/...
* **Length** = Average of subfeed lengths * # of Units
* **Count** = # of Units
## Inner Duct
For future use (e.g. fiber)
`COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/`INNERDUCT`/`... (GP)`
1. `TEMPORARY ITEMS`/`MaxCell 3" 3 Cell`
* **Material Price** = 450.00/C
* **Labor Hours** = 12.00/C
Alternative
1. `COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/`INNERDUCT`/`... (GP)`
## Devices
As shown on plans. Ignore floor boxes, other electrical scope.
`COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/...
* .../`BOH / AMENITY ASSEMBLIES`
* .../`SCREWLESS DECORA COVERS UNITS / BOH`
* .../`ROUGH IN ASSY`
1. `COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/...
* .../`BOH / AMENITY ASSEMBLIES`
* .../`SCREWLESS DECORA COVERS UNITS / BOH`
* .../`ROUGH IN ASSY`
If system is included, take off _both_ rough-in and device assemblies
in amenity areas.