### 1. Estimate preparation
1. Locate Unit panels and relevant keynotes
* Bus amps
* bus amps
2. Read about the project specifications and construction type
* Wood or Metal studs
* wood or metal studs
* wiring methods
* NM or MC
* Wiring device plates
* wiring device plates
* Decora or Standard
* Wiring device specs
* wiring device specs
* are 15A devices allowed?
* Equipment (20A Kitchen and bath)
* equipment (20A Kitchen and bath)
3. Fill out OneNote
1. Fill out OneNote
#### Load Centers
| Rating | Assembly |
| ------- | ---------------------------------------------------------------------------------- |
| <= 100A | `DIST PANELS & UNIT LOAD CENTERS`/`UNIT LOAD CENTERS - ...`/`... UNIT LOAD CENTER` |
| > 100A | `DIST PANELS & UNIT LOAD CENTERS`/`UNIT LOAD CENTERS - ...`/`... BREAKER PNL` |
#### Shade Control
#### "High Lows"
`COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/`UNIT DATA - TELECOM`/`HIGH-LOW - TV SCOOP 1 1/2" ENT - NO CABLE`
#### Air Sealing
* LEED Silver
* Draft Proof Box
* Mid-Atlantic jobs
`ITEM DATABASE`/`BOSES & CABINETS`/`BOXES - VAPOR`
`COMMON ASSEMBLIES`/`UNITS - MC CABLE ASSEMBLIES`/`GENERAL ASSEMBLIES - METAL STUD`/`UNIT MISC ITEMS - MC - ADJUST ACCORDINGLY`
### 2. Takeoff