vault backup: 2025-07-22 16:59:59

This commit is contained in:
2025-07-22 16:59:59 -04:00
parent dcfb706425
commit 4e829fa06c
40 changed files with 900 additions and 282 deletions
+59 -31
View File
@@ -1,14 +1,21 @@
---
id: electrical
aliases: []
tags: []
---
# Final SOE
## 1. Trash Chute
- Check elevations for floor height
- Uncheck Link 'Enable Livecount'
- CA.33(Misc. Ass.). 2
- 100' Horizontal (If not shown)
- Vertical Put in Typical
Horizontal:
- Check if shown on power drawings as mech connection
- If not, use 100ft length
- Check Bottom of chute if taken off already in elec. THIS IS ONLY FOR THE HORIZONTAL
Vertical (Riser):
- Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...`
- Uncheck Link 'Enable Livecount'
- Takeoff in Typical
- Length = average floor to floor height
## 2. CU/IP
@@ -17,46 +24,67 @@
## 3. Slab Deck
- Create Area Typical for every Concrete slab floor
- ID.37.16.1
- ID. MISC PDI PRODUCT. MISC MATERIAL. SLAB/DECK
- 2 Typicals
Create Area Typicals for every Concrete slab floor:
- 'All Building'
- 1 every level (Not Roof)
- HD 1 Per Section
- 1 every level (Not Roof)
- HD: 1 Per Section
- 'All Garage'
- 1 every level
- 1 every level
- Takeoff: `ITEM DATABASE`/`MISC PDI PRODUCT`/`MISC MATERIAL - SLAB/DECK & FEEDER`/`MISC MATERIAL - SLAB/DECK (NAILS, PAINT, TAPE, ETC = $250)`
- 1 Takeoff each Typical, Count = 1
## 4. Temporary Power & Lighting
### 4.1 Temp Power
```
Area = ""
Area = "2 - Site"
Phase = "Temp Power"
System = "TPS - Temp Power Service (Site)"
BidItem = "1 - Site"
```
Hoxton Hotel (aka Nashville Hotel)
- Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - * SERVICE`
### 4.2A Temp Lighting (Building)
```
Area = "01 - Temp Power Distribution Building"
Phase = "Temp Power"
System = "TPD - Temp Power Distribution (Gag. & Bldg.)"
BidItem = "3 - Building"
```
- ID.27.
- 3/4/5 (A-bid>>)
- 8/9
- Total GSF - Garage GSF = Building Size
- Garage SF = Temp lighting Garage
- Enter in count
- Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)`
- *Count* = Building Size = Total GSF - Garage GSF
Gardens: Take off 1 Tpole `ID.28.1` per 150' per building
Garden Styles:
- Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - T POLE (EACH)`
- *Count* = 1 per 150' per building
TEMP LIGHTING ^^^^
### 4.2B Temp Lighting (Garage)
```
Area = "01 - Temp Power Distribution Building"
Phase = "Temp Power"
System = "TPD - Temp Power Distribution (Gag. & Bldg.)"
BidItem = "3 - Building"
```
- Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)`
- *Count* = Garage SF
## 5. Irrigation pumps
- SYSTEM: `MISC - Site Miscellaneous`
```
Area = "2 - Site"
Phase = "Temp Power"
System = `MISC - Site Miscellaneous`
BidItem = "1 - Site"
```
- (3) 3Phase 30A 200' Mech. Con.
- Append to name: "Irrigation Pump - "
## 6. Lightning Protection
- Check line Item on Proposal
- Go to the notes and take off
- Append to name: "Irrigation Pump - "