# Lighting Takeoff (Fixtures)
# Lighting (Fixtures)
## Naming
## Info
### Format
## Scope
### Building Designations
#### Naming
##### Format
```regex
<phase-abbr> - <assembly>(\: <subtype>)?( - <fixture-labor>)? \(<wiring-method>\)( <wm-descriptor>)* <branch-length>ft
@@ -11,7 +17,7 @@
> [!example]
> `A - Surface: Pendant - 2.0hrs (MC) LV 20ft`
### Order
#### Order
Use empty designations to separate phases.
@@ -28,7 +34,7 @@ Use empty designations to separate phases.
> CU - Surface: Wall (MC) LV 25ft
> ```
## Fixture Labor
#### Fixture Labor
> | Fixture Type | Labor |
> | ------------ | -------------- |
@@ -41,7 +47,7 @@ Use empty designations to separate phases.
>
> [^1]: Determine exact labor from fixture and size.
## Fixture Branch Length
#### Fixture Branch Length
> | Case | Standard Length |
> | ------------- | --------------- |
@@ -58,7 +64,7 @@ Use empty designations to separate phases.
>
> [^2]: See fixture types below for special cases.
## Fixture Branch Wire size
#### Fixture Branch Wire size
> | Case | Wire Size |
> | -------------- | --------- |
@@ -71,9 +77,9 @@ Use empty designations to separate phases.
>
> [^2]: Kitchen and bathroom fixtures shall be #12 (NOT #14) on wood frame (NM) projects.
## Garage
#### Garage
### Fixtures
#### Fixtures
Use ENT Assembly unless spec requires otherwise.
@@ -87,7 +93,7 @@ If PVC, use following assemblies:
| Ceiling | `PVC/ENT ASSEMBLIES`/`... - SLAB BOX / 45 DEG STUBBY` |
| Wall | `PVC/ENT ASSEMBLIES`/`... - STL BOX & TILE RING / 45 DEG STUBBY/ ENT DROP` |
### Homeruns
#### Homeruns
> `System` = "EL - Electrical"
@@ -95,13 +101,14 @@ Use 1 Homerun for every 3 circuits in Garage
Use assembly `Common Assemblies`/`Device Homeruns in Slab/Deck`
## Surface Mount
#### Surface Mount
* Wall Mount (Sconce)
* Pendant
* Linear
* Tape
* Track
> [!info] Surface Mount Fixtures
> * Wall Mount (Sconce)
> * Pendant
> * Linear
> * Tape
> * Track
| Wiring Method | Assembly Path |
| ---------------------------------------------------------------------------- |
@@ -114,7 +121,7 @@ Use assembly `Common Assemblies`/`Device Homeruns in Slab/Deck`
> [!note]
> Use lighting control cable assemblies in Amenity areas
### Tape Lighting
##### Tape Lighting
Also called "cove" or "strip",
however those terms are less specific
@@ -132,34 +139,24 @@ and change `Fct 1` to match the calculated labor.
Separate these fixtures by labor, not length
```
A - Tape 0.5hr (1-6ft) - MC #12 40ft
A - Tape 1.0hr (7-12ft) - MC #12 40ft
A - Tape 1.5hr (13-18ft) - MC #12 40ft
A - Tape 2.0hr (19-24ft) - MC #12 40ft
A - Tape 2.5hr (25-30ft) - MC #12 40ft
A - Tape 3.0hr (31-36ft) - MC #12 40ft
A - Tape 3.5hr (37-42ft) - MC #12 40ft
A - Tape 4.0hr (43-48ft) - MC #12 40ft
A - Tape 4.5hr (49-54ft) - MC #12 40ft
A - Tape 5.0hr (55-60ft) - MC #12 40ft
A - Tape 5.5hr (61-66ft) - MC #12 40ft
A - Tape 6.0hr (67-72ft) - MC #12 40ft
A - Tape 6.5hr (73-78ft) - MC #12 40ft
A - Tape 7.0hr (79-84ft) - MC #12 40ft
A - Tape 7.5hr (85-90ft) - MC #12 40ft
A - Tape 8.0hr (91-96ft) - MC #12 40ft
A - Tape 8.5hr (97-102ft) - MC #12 40ft
A - Tape 9.0hr (103-108ft) - MC #12 40ft
A - Tape 9.5hr (109-114ft) - MC #12 40ft
A - Tape 10.0hr (115-120ft) - MC #12 40ft
A - Surface: Tape - 0.5hr (01-06ft) - MC #12 40ft
A - Surface: Tape - 1.0hr (07-12ft) - MC #12 40ft
A - Surface: Tape - 1.5hr (13-18ft) - MC #12 40ft
A - Surface: Tape - 2.0hr (19-24ft) - MC #12 40ft
A - Surface: Tape - 2.5hr (25-30ft) - MC #12 40ft
A - Surface: Tape - 3.0hr (31-36ft) - MC #12 40ft
A - Surface: Tape - 3.5hr (37-42ft) - MC #12 40ft
A - Surface: Tape - 4.0hr (43-48ft) - MC #12 40ft
A - Surface: Tape - 4.5hr (49-54ft) - MC #12 40ft
```
## Recessed
#### Recessed
* recessed downlight
* recessed linear
* wall grazer
* troffer
> [!info] Recessed Fixtures
> * recessed downlight
> * recessed linear
> * wall grazer
> * troffer
| Wiring Method | Assembly Path |
| ------------- | ------------------------------ |
@@ -173,7 +170,7 @@ round up to the nearest 5ft
> [!note]
> "HI HAT" refers to a recessed can fixture.
## Undercabinet Fixtures
#### Undercabinet Fixtures
| Wiring Method | Assembly Path |
| ------------- | ------------------------------------- |
@@ -183,9 +180,9 @@ round up to the nearest 5ft
> [!note]
> Takeoff 2 fixtures if jumping over oven
Use 10ft #12/2 for MC & NM
Use 10ft \#12/2 for MC & NM
## Paddle Fans
#### Paddle Fans
| Wiring Method | Assembly Path |
| ------------- | ----------------------------------------------------- |
@@ -193,11 +190,11 @@ Use 10ft #12/2 for MC & NM
| MC Cable | `MC ASSEMBLIES`/`FAN RATED OCT BOX W/ BAR HNGR - ...` |
| PVC | `PVC/ENT ASSEMBLIES`/`... - SLAB BOX / 45 DEG STUBBY` |
## Stairwells & Elevators
#### Stairwells & Elevators
`PVC/ENT ASSEMBLIES`/`... - SLAB BOX / 45 DEG STUBBY`
## Facade
#### Facade
> `Phase` = "Facade"
@@ -211,24 +208,25 @@ Length and Labor will be more than a normal fixture in BOH/Amenity
> 1. `3/4" PVC W/ 3#10 - STL BOX & TILE RING / 45 DEG STUBBY/ ENT DROP`
> * `Length per Unit` = Distance to panel
## Porte Cochere (Drive up Area)
#### Porte Cochere (Drive up Area)
Create its own breakout in WBS, and phase in Accubid
This is not technically exposed or drop ceiling, but still use PVC
> [!quote]
> This is not technically exposed or drop ceiling, but still use PVC
## FAA Lighting
#### FAA Lighting
> 1. `FIXTURE LABOR`/`FIXTURE LABOR 1HR`
> 2. `FESTOON & ROOF ASSEMBLIES`/`Aircraft Warning, 3/4" Conduit GRC/PVC 2#10, 1#10G`
# Site & Courtyard
### Site & Courtyard
## Breakdowns
#### Breakdowns
> `System` = "FML - Site Fixtures Material & Labor"
> System: "FML - Site Fixtures Material & Labor"
## Fixture Assemblies
#### Fixture Assemblies
> | Fixture Type | Assembly Path |
> | ------------------------------------ | -------------------------------------------------------------------------------- |
@@ -243,12 +241,14 @@ This is not technically exposed or drop ceiling, but still use PVC
>
> [^2]: Per Corwin: Hand rail lights should have a rigid 90 stub up and some flex
### Festoon Lighting
##### Festoon Lighting
AKA "string" or "market" lights
> AKA "string" or "market" lights
> 1. `FIXTURE LABOR`/`FIXTURE LABOR 2HR`
> 2. `FESTOON & ROOF ASSEMBLIES`/`FESTOON CABLE HANGER & EYE BOLTS - LENGTH`
> * `Length per Unit` = Light string length
> 3. `COURTYARDS & LANDSCAPE`/`ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...`
> * `Length per Unit` = Distance to panel + 15ft
### Takeoff