@@ -68,12 +68,14 @@ Locate:
> All takeoffs in Systems with names including "site"
> should be in "Site" Area, Phase, and Bid Item breakdowns.
For adjacent panels, use a minimum 10ft length.
#### Adders
Use the difference in elevation between equipment
or 10ft, whichever is greater.
Add an additional 5ft for site runs
Add an additional 5ft (total 15ft) for site runs
(primaries, secondaries, etc.).
#### Primaries
@@ -82,14 +84,18 @@ Empty conduit.
#### Secondaries
> [!info] Vaults and Secondary Connections
> In utility vaults, secondary conductors sometimes run on racks,
> far past their entrance conduits, to their transformers.
> It is necessary to add this distance to the wire makeup,
> rather than simply measure the conduit assembly to the transformer.
##### Wiring on Vault Racks
Where secondary conductors run on racks in utility vaults
manually set the length of conduit,
measure the wire length,
add 20ft in addition to previously mentioned adders.
#### Feeders
`Area` = "01 - Feeders/Risers Building"
for all feeders, no matter the location.
#### Bus Duct
`COMMON ASSEMBLIES`/`DISTRIBUTION`/`BUS DUCT`