@@ -68,12 +68,14 @@ Locate:
|
||||
> All takeoffs in Systems with names including "site"
|
||||
> should be in "Site" Area, Phase, and Bid Item breakdowns.
|
||||
|
||||
For adjacent panels, use a minimum 10ft length.
|
||||
|
||||
#### Adders
|
||||
|
||||
Use the difference in elevation between equipment
|
||||
or 10ft, whichever is greater.
|
||||
|
||||
Add an additional 5ft for site runs
|
||||
Add an additional 5ft (total 15ft) for site runs
|
||||
(primaries, secondaries, etc.).
|
||||
|
||||
#### Primaries
|
||||
@@ -82,14 +84,18 @@ Empty conduit.
|
||||
|
||||
#### Secondaries
|
||||
|
||||
> [!info] Vaults and Secondary Connections
|
||||
> In utility vaults, secondary conductors sometimes run on racks,
|
||||
> far past their entrance conduits, to their transformers.
|
||||
> It is necessary to add this distance to the wire makeup,
|
||||
> rather than simply measure the conduit assembly to the transformer.
|
||||
##### Wiring on Vault Racks
|
||||
|
||||
Where secondary conductors run on racks in utility vaults
|
||||
manually set the length of conduit,
|
||||
measure the wire length,
|
||||
add 20ft in addition to previously mentioned adders.
|
||||
|
||||
#### Feeders
|
||||
|
||||
`Area` = "01 - Feeders/Risers Building"
|
||||
for all feeders, no matter the location.
|
||||
|
||||
#### Bus Duct
|
||||
|
||||
`COMMON ASSEMBLIES`/`DISTRIBUTION`/`BUS DUCT`
|
||||
|
||||