title: 2025-11-04 Belle Meade Director Review
---
# 2025-11-04 Belle Meade Director Review
## Takeoff Review
Reviewed takeoff by system.
### Retail Village Temporary Power
Joel changed square foot budgets to temporary pole budgets only
due to minimal scope (warm shell).
### Generator Scope
Confirmed generator quotes include furnishing docking station.
### Feeder Lengths
Confirmed validity of longer feeder lengths:
Generator to Tower B
### Grounding
Takeoff appears to be missing some or all grounding.
To be added if necessary.
### Subfeed Sizing
Based on ampacity, subfeeds are oversized.
Sizing was per feeder schedule.
Takeoff approved unchanged.
### Undercabinet Wiremold
Multi-outlet assemblies above unit kitchen countertops were not taken off,
nor was branch wiring for the same.
Joel to confirm takeoff requirement with bid.
### Amenity Homeruns
No homeruns for amenity lighting or electrical were taken off.
Joel to add these.
> [!info] Circuits per Raceway
> Corwin stated that---assuming no overriding specification---
> up to 6 circuits in a raceway are permissible.
### Lighting Control
Lighting control takeoff was reviewed,
no changes were recommended.
> [!info] Lighting Control Pre-Work
> Corwin stated that with the imminent changes to lighting control takeoff,
> it will be necessary for estimators to more intently consider the design:
> noting quantities of lighting zones and controllers,
> even where not explicitly shown.
### Telecom
Confirmed unit telecom requirements.
Backbone was mistakenly taken off in Telecom.
### Retail Fire Alarm
Retail village fire alarm devices were taken off free-air,
Joel to substitute for EMT.
## Extension Review
Reviewed extension quantities and costs.
Of particular note were:
* conduit
* wire
* cable
* wiring devices
## Labor Plan Review
Hours per square foot was lower than expected,
this was rationalized as being due
to the relatively high portion of garage and shell retail space.
%%
"Openings per unit" was another metric considered---
higher than expected in this case---
however I didn't catch the significance of this.
%%