id:
|
||||
aliases: []
|
||||
title: "PDI Accubid Closeout: Quoted Material"
|
||||
tags:
|
||||
- authorship/original
|
||||
- destiny/permanent
|
||||
- occupational/closeout
|
||||
- status/incomplete
|
||||
- type/guide
|
||||
dg-publish: true
|
||||
---
|
||||
# PDI Accubid Closeout: Quoted Material
|
||||
|
||||
> [!important]
|
||||
> Quoted material costs must be ==pre-tax==.
|
||||
|
||||
## Fixtures
|
||||
|
||||
* **Vendor** <- "PDR - {Quote Type}" (e.g. "PDR - Spec/Equal", "PDR - VE")
|
||||
* **Quote** <- Per PDI Systems proposal
|
||||
* **Notes** <- Quote date
|
||||
|
||||
> [!tip]
|
||||
> PDR fixture quotes are usually broken out by area type.
|
||||
> It is not necessary to preserve these breakdowns in the estimate.
|
||||
> Use the sum total cost in a single Quoted Materials line item.
|
||||
|
||||
## Switchgear
|
||||
|
||||
* **Vendor** <- Per quote (or "PDI BUDGET" if not available)
|
||||
* **Quote** <- Per quote (or Bid Sheet Budget if not available)
|
||||
* **Notes** <- Quote Date
|
||||
|
||||
## Generator
|
||||
|
||||
* **Vendor** <- Per quote (or "PDI BUDGET" if not available)
|
||||
* **Quote** <- Per quote (or Bid Sheet Budget if not available)
|
||||
* **Notes** <- Quantity, Size in kW, Quote Date
|
||||