@@ -35,4 +35,4 @@ and estimation
|
||||
It's not engineering to budget for the most likely case.
|
||||
|
||||
Estimators need not know _why_ there tends to be ~~example~~,
|
||||
they need need only have basis for applying that generalization to another project.
|
||||
they need only have basis for applying that generalization to another project.
|
||||
|
||||
@@ -12,7 +12,7 @@ daily: "[[2025-10-31]]"
|
||||
_Friday Evening_
|
||||
|
||||
This morning as I was leaving for work I saw a massive congregation
|
||||
of all the walky water birds I love so much. A hundred and more, milling about
|
||||
of all the walky water [[birds]] I love so much. A hundred and more, milling about
|
||||
in-the early sunrise. The banks were covered in ibises picking at the grass
|
||||
around the feet of egrets standing proudly and spaced just so. A dozen anhingas
|
||||
splashed messily in the center of the pond while a lone stork looked on with
|
||||
|
||||
@@ -13,8 +13,8 @@ _Saturday Morning_
|
||||
Somehow I've already let an hour get away from me.
|
||||
Today I need to do some cleaning: a load of laundry and leftover dishes
|
||||
at least. I'll do those after I finish this note, plus some pushups, before
|
||||
I shower and change to go visit the birds across the street. Later I'll need
|
||||
to go to the store for more sliced almonds and coconut oil so I can make granola
|
||||
I shower and change to go visit the [[birds]] across the street. Later I'll need
|
||||
to go to the store for more sliced almonds and coconut oil so I can make [[granola]]
|
||||
for tomorrow's breakfast. I'll go to Walmart so I can get a new mattress
|
||||
protector, too. Copy paper, a 3-hole punch and a small binder would also be
|
||||
nice for my typewriter journaling.
|
||||
|
||||
@@ -12,4 +12,4 @@ _Saturday Morning_
|
||||
|
||||
I wasted more time doomscrolling after my last note, but I did manage
|
||||
to do the laundry, dishes, and pushups. Now I need to shower and dress in time
|
||||
to see the birds.
|
||||
to see the [[birds]].
|
||||
|
||||
@@ -10,8 +10,8 @@ daily: "[[2025-11-01]]"
|
||||
# 2025-11-01 08:25:??
|
||||
|
||||
There were fewer than yesterday, but still a ton. There was a chill, but
|
||||
I was dressed well for it. I think with exposure the birds will get used to
|
||||
mg presence. I saw a bald eagle (_Haliaeetus leucocephalus_) for the first time
|
||||
I was dressed well for it. I think with exposure the [[birds]] will get used to
|
||||
my presence. I saw a bald eagle (_Haliaeetus leucocephalus_) for the first time
|
||||
in Florida. They are ugly creatures, of both body and spirit, unlike the wood
|
||||
stork (_Mycteria americana_) which is uglier of body, but pure of heart.
|
||||
There was also some guy getting dumped on the phone and not taking it well.
|
||||
|
||||
@@ -36,10 +36,9 @@ This analysis of 334.12(A)(2) is flawed.
|
||||
Based on the [[nfpa-70_100_definitions|Article 100]] definitions
|
||||
of [[nfpa-70_100_definitions#Exposed (as applied to wiring methods).|exposed]]
|
||||
and [[nfpa-70_100_definitions#Dwelling, Multifamily.|dwelling]],
|
||||
[[nfpa-70_334_nm-cable#334.12(A) Types NM and NMC.|334.12(A)(2)]]
|
||||
can be paraphrased as follows:
|
||||
334.12(A)(2) can be paraphrased as follows:
|
||||
|
||||
> [!cite] NEC 334.12(A)(2), pp.
|
||||
> [!cite] [[nfpa-70_334_nm-cable#334.12(A) Types NM and NMC.|NEC 334.12(A)(2)]], pp.
|
||||
> Types NM and NMC cable are not permitted to be installed
|
||||
> in accessible spaces above suspended ceilings,
|
||||
> _except in buildings containing one or more dwelling units._
|
||||
|
||||
@@ -10,9 +10,9 @@ daily: "[[2025-11-11]]"
|
||||
|
||||
_Tuesday Morning, Before Work_
|
||||
|
||||
One of the most appealing aspects of estimating
|
||||
One of the most appealing aspects of [[construction-estimating]]
|
||||
to me is the dynamic we have with our employers.
|
||||
my experience was at Ace that estimators act like,
|
||||
my experience was at [[ace-electric-inc|Ace]] that estimators act like,
|
||||
and are treated like good artists, like loveable
|
||||
little scamps who always get into trouble, but
|
||||
you keep them around because they do good work.
|
||||
|
||||
@@ -9,11 +9,11 @@ daily: "[[2025-11-11]]"
|
||||
---
|
||||
# 2025-11-11 14:41:??
|
||||
|
||||
I just saw a post on a construction estimators forum
|
||||
I just saw a post on a [[construction-estimating|construction estimators]] forum
|
||||
from a user lamenting that their coworkers and customers
|
||||
largely do not understand the difference between markup and margin.
|
||||
|
||||
It made me remember the micro-debates about that I would have with Dale
|
||||
It made me remember the micro-debates about that I would have with [[dale-flythe|Dale]]
|
||||
every time we were closing out an estimate.
|
||||
This is the example I would always give
|
||||
while trying to explain it to him.
|
||||
|
||||
@@ -7,7 +7,7 @@ daily: "[[2025-11-13]]"
|
||||
---
|
||||
# 2025-11-13 08:03:??
|
||||
|
||||
I was thinking about recent critiques of my writing style
|
||||
I was thinking about recent critiques of my [[writing]] style
|
||||
and how they don't really apply to my speech,
|
||||
even though I don't imagine myself approaching them differently.
|
||||
|
||||
|
||||
@@ -10,7 +10,7 @@ daily: "[[2025-11-13]]"
|
||||
|
||||
I'm still working on articulating
|
||||
my main difficulty in the transition
|
||||
from Ace to PDI estimating.
|
||||
from [[ace-electric-inc|Ace]] to [[power-design-inc|PDI]] estimating.
|
||||
|
||||
At a high level,
|
||||
it's that our process is built on _instrumental_ methods,
|
||||
|
||||
@@ -38,10 +38,7 @@ Fire stopping budget = $25-35 per Unit.
|
||||
Robotic Total Station hours: match Structural Foreman.
|
||||
|
||||
For contracts 5--15 million dollars:
|
||||
|
||||
$$
|
||||
\text{Equipment Cost} \approx 1\%
|
||||
$$
|
||||
Equipment Cost $$\approx$$ 1% of Contract Value
|
||||
|
||||
Mid Atlantic: 1 trip per month
|
||||
|
||||
|
||||
@@ -9,6 +9,12 @@ daily: "[[2025-11-21]]"
|
||||
---
|
||||
# 2025-11-21 10:11:??
|
||||
|
||||
## "Hours Burned vs. Hours Earned"
|
||||
|
||||
%%
|
||||
A criticism of [[earned-value-management]] in [[construction]].
|
||||
%%
|
||||
|
||||
> [!quote] [ELECTRI's Industry Benchmarking Tool - ELECTRI International](https://www.electri.org/research-overview/electris-industry-benchmarking-tool/)
|
||||
> ### Hours Burned vs. Hours Earned
|
||||
>
|
||||
@@ -23,7 +29,7 @@ This is a terribly problematic metric.
|
||||
If a project went over its material budget
|
||||
despite standard rigorous oversight
|
||||
where would you first look,
|
||||
construction or estimating?
|
||||
operations or estimating?
|
||||
In almost all cases the safer bet is estimating.
|
||||
Why should labor be different?
|
||||
|
||||
@@ -31,6 +37,4 @@ Wherever there is budget variance
|
||||
there is a persistent tendency to blame construction
|
||||
before estimating.
|
||||
|
||||
[[earned-value-management-in-construction-estimating]]
|
||||
|
||||
[[purpose-of-construction-estimating#The Myth of Estimate Accuracy]]
|
||||
|
||||
@@ -9,6 +9,11 @@ daily: "[[2025-11-24]]"
|
||||
|
||||
## Extracting PDF Panel Schedules
|
||||
|
||||
%%
|
||||
steps to extract panel schedule data
|
||||
from [[pdf]] drawings
|
||||
%%
|
||||
|
||||
Extract relevant pages
|
||||
|
||||
Crop Sheet Titles
|
||||
|
||||
@@ -8,7 +8,7 @@ daily: "[[2025-12-02]]"
|
||||
|
||||
### Set Notation Example
|
||||
|
||||
Let $A$ and $B$ be sets
|
||||
Let $A$ and $B$ be [[set-theory|sets]]
|
||||
sharing some but not all elements.
|
||||
|
||||
* $A \cap B \neq \varnothing$:
|
||||
|
||||
@@ -8,6 +8,11 @@ daily: "[[2025-12-02]]"
|
||||
|
||||
### Panel Schedule Relationship Diagram
|
||||
|
||||
%%
|
||||
brainstorming abstractions for `Panelboard` objects,
|
||||
possibly for use in custom [[construction-estimating-software]].
|
||||
%%
|
||||
|
||||
#### Sections
|
||||
|
||||
A panelboard with multiple sections
|
||||
|
||||
@@ -14,7 +14,7 @@ and as frameworks for general decision-making.
|
||||
The idea that one could devote significant thought
|
||||
into making a decision aligned with their [[personal-values]]
|
||||
and fail to pick the best option to that end is intriguing to me,
|
||||
more so that an accurate quantization of ones values
|
||||
moreso that an accurate quantization of ones values
|
||||
and that the appropriate framework could trivialize all such decisions.
|
||||
|
||||
Personal decision-making is often described
|
||||
|
||||
@@ -8,6 +8,8 @@ daily: "[[2026-02-12]]"
|
||||
---
|
||||
# 2026-02-12 09:49:56
|
||||
|
||||
[[electrical-construction]]
|
||||
|
||||
### Interrupting Rating
|
||||
|
||||
* "short-circuit interrupting rating"
|
||||
@@ -25,7 +27,8 @@ Measured in amperes, usually shown as kAIC.
|
||||
|
||||
[[nfpa-70_110_requirements#^10|NEC 110.10 Circuit Impedance, Short-Circuit Current Ratings, and Other Characteristics.]]
|
||||
|
||||
Applies to **assemblies**: distribution equipment like switchboards, panelboards, switches, etc.
|
||||
Applies to **assemblies**: distribution equipment
|
||||
like switchboards, panelboards, switches, etc.
|
||||
|
||||
Maximum current that the equipment can withstand
|
||||
in a short-circuit event without damage.
|
||||
|
||||