occupational/closeout
2025-11-18

2025-11-18 16:33:??

Elliot St. ConEst Senior Review

%% Transcription of notes taken while reviewing elliott-st-hotel with joel-jansen. %%

Adorne USB Heating Designation was built with standard device. Subbed for Adorne.

Subbed standard duplex receptacles in guestrooms for Adorne.

Confirmed fixture branch length changes including Garage

Note: It is not usually necessary to count emergency fixtures separately.

Use minimum 1 hour for tape lights, except in units (minimum 0.5hr).

Final Pricing adjustments:

  • Warranty,
  • CIP (see proposal)

Added putty pads.

Fire stopping budget = $25-35 per Unit.

Robotic Total Station hours: match Structural Foreman.

For contracts 5--15 million dollars: Equipment Cost \approx 1% of Contract Value

Mid Atlantic: 1 trip per month

Offsite Parking: see bid sheet

Project Executive time same as Oversight.

When calculating durations for indirect labor, round down.

  • Rough Foreman
  • Trim Foreman
  • Amenity Foreman

LV/FA Foreman: get hours from systems quote.

Fire Alarm, Two-Way Communication, DAS: Phase = "Fire Alarm"

Erroneously used WP GFI's in bathrooms, subbed for Kitchen/Bath assembly.