title: PDI Accubid Equipment
|
|
tags:
|
|
- occupational/closeout
|
|
- type/guide
|
|
up: "[[pdi-accubid-closeout]]"
|
|
---
|
|
# PDI Accubid Closeout: Equipment
|
|
|
|
> [!important] Disclaimer
|
|
> This is my interpretation of what is meant by the cost names,
|
|
> not necessarily how each is used in practice.
|
|
> To that, it appears many are not used at all.
|
|
|
|
Clear **Markup %** for all lines.
|
|
|
|
> [!tip]
|
|
> Reference similar jobs for equipment allocation.
|
|
> Total cost is expected to be ~1% of Base Bid
|
|
|
|
`SITE OFFICE TRAILER (per Month)`
|
|
|
|
As stated.
|
|
|
|
`SITE STORAGE 40' CONNEX (per Month)`
|
|
|
|
As stated.
|
|
|
|
`Mobile Lock (formerly TattleTale)`
|
|
|
|
Crew phone storage
|
|
|
|
`AUGER ON BOBCAT (per pole)`
|
|
|
|
Augur hole for site pole foundation
|
|
|
|
`MINI EXCAVATOR (per Month)`
|
|
`EXCAVATOR - 11,000LB HYDRAULIC (per Month)`
|
|
`BACKHOE 4WD (per Month)`
|
|
`BACKHOE 4WD W/ OPERATOR (per Month)`
|
|
|
|
Conventional excavation.
|
|
Which is optimal is subject to debate
|
|
based on exact scenario.
|
|
|
|
`BOBCAT (per Month)`
|
|
|
|
Skid-steer loader.
|
|
Can be fitted with specialized attachments:
|
|
Forks, augur, dozer bucket, etc.
|
|
|
|
`DITCH WITCH WB (per Month)`
|
|
`DITCH WITCH RIDE ON (per Month)`
|
|
|
|
Less versatile excavation machine
|
|
|
|
"WB" = Walk-Behind
|
|
|
|
`PLATE COMPACTOR (per Month)`
|
|
|
|
Also called "tamps" or "tampers",
|
|
Used to compact backfilled soil.
|
|
|
|
`ELECTRIC BENDER 2" (per Month)`
|
|
`HYDRAULIC BENDER 4" (per Month)`
|
|
|
|
For bending conduit larger than 1-1/4".
|
|
|
|
`WIRE PULLER (per Month)`
|
|
|
|
Nickname "tugger".
|
|
|
|
`THREADER - HANDHELD 2" (per Month)`
|
|
`THREADER - HD MOUNT 4"(per Month)`
|
|
|
|
For field threading RMC and IMC conduit.
|
|
|
|
`HYPRESS TOOL (per Week)`
|
|
|
|
For crimping conductor compression fittings.
|
|
|
|
`HI POT TESTER (per Week)`
|
|
|
|
Megohmmeter.
|
|
Nickname "Megger".
|
|
Used to verify conductor insulation integrity after install.
|
|
|
|
`UTV (per Month)`
|
|
|
|
Utility Terrain Vehicle
|
|
Like a fancy golf cart.
|
|
Used to transport privileged individuals about the job site.
|
|
|
|
`MANLIFT - 40' (per Month)`
|
|
`MANLIFT - 80' (per Month)`
|
|
|
|
Single worker lift.
|
|
Trade name "Genie".
|
|
|
|
`CRANE - 50 TON (per Day)`
|
|
|
|
Large equipment handling:
|
|
switchgear, generators, etc.
|
|
|
|
`PUMP 2" W/ 20' HOSE (per Month)`
|
|
|
|
Used for excavation dewatering.
|
|
|
|
`FORKLIFT (per ...)`
|
|
|
|
Conventional forklift.
|
|
|
|
`LULL / SHOOTING BOOM LIFT (per ...)`
|
|
|
|
Telehandler forklift
|
|
|
|
`SCISSOR LIFT - 19' (per ...)`
|
|
|
|
Working platform for multiple
|
|
|
|
`CONCRETE SAW (per ...)`
|
|
|
|
As stated.
|
|
Should not usually be necessary for new construction.
|
|
|
|
`ROAD PLATES - 8X12 STEEL TRAFFIC RATED`
|
|
|
|
For covering trenches through roadways.
|
|
|
|
`TRENCH BOX - 10x10 STEEL TRENCH BOX 4" WALL`
|
|
|
|
Trench wall support,
|
|
necessary for large excavations.
|
|
|
|
`TWO-WAY RADIO`
|
|
|
|
As stated.
|
|
Often replaced by cell phones.
|
|
|
|
`TOTAL STATION (per Month)`
|
|
|
|
Robotic Total Station (RTS)
|
|
|
|
Survey equipment used to layout equipment:
|
|
usually light fixtures, site or interior.
|