title: Pre-Takeoff Research
|
|
tags:
|
|
- occupational
|
|
- type/guide
|
|
---
|
|
# Pre-Takeoff Research
|
|
|
|
%%
|
|
This note should be arranged chronologically:
|
|
%%
|
|
|
|
%%
|
|
## Requirement Sources
|
|
|
|
* Drawings
|
|
* Project Manual (Specifications)
|
|
* GC Narrative
|
|
* GC verbal direction
|
|
* [[pdi-bid-estimating|Bid]] proposal
|
|
* Bid verbal direction
|
|
|
|
%%
|
|
|
|
> [!important] Requirement Precedence
|
|
> In case of conflict:
|
|
> Requirements of the plans and specs
|
|
> are superseded by the terms of our proposal,
|
|
> which are superseded by specific direction from the bid team.
|
|
|
|
%%
|
|
Where NEC, IBC, and other applicable codes fall in this hierarchy
|
|
is subject to some debate.
|
|
%%
|
|
|
|
> [!aside] "Plans & Specs"
|
|
> The oft repeated "per plans and specs" is a gross oversimplification:
|
|
> The RFP documents will---more likely than not---
|
|
> have one or more irreconcilable contradictions,
|
|
> or some instance of [[gold-plating]] too egregious to accept.
|
|
> When ConEst takes off a project "per plans and specs",
|
|
> we are taking off _Bid's interpretation_ of the RFP documents,
|
|
> which they must be able to articulate.
|
|
|
|
%%
|
|
The limitations of Bid's authority are currently being questioned,
|
|
%%
|
|
|
|
Seek to use the cheapest method
|
|
(as determined by Senior Construction Estimator
|
|
and Database Administrator),
|
|
as allowed for the situation.
|
|
|
|
* [[wiring-method-selection]]
|
|
* [[wiring-device-research]]
|
|
* [[emergency-systems-research]]
|
|
* [[low-voltage-raceway-selection]]
|
|
|
|
## General
|
|
|
|
Read about the project specifications and construction type:
|
|
* Delivery Method: (Plans & Specs, Design Build, Design Assist, Preliminary Budget)
|
|
* Deck thickness
|
|
* Wiring methods
|
|
* Conductor material
|
|
|
|
Locate:
|
|
* Main Electrical rooms and panel locations
|
|
|
|
## By System
|
|
|
|
### Feeders
|
|
|
|
Read about the project specifications and construction type:
|
|
* Deck thickness
|
|
* Wiring methods
|
|
* Conductor material
|
|
* Wire terminations (mechanical acceptable or compression required?)
|
|
|
|
Locate:
|
|
* Riser Diagram
|
|
* Feeder Schedule (if present)
|
|
|
|
### Subfeeds
|
|
|
|
1. Read about the project specifications and construction type
|
|
* Corridor Ceiling type
|
|
|
|
2. In the drawings, locate:
|
|
* Unit Panel Schedules
|
|
* bus amps
|
|
* Unit Load Calculations
|
|
* Subfeed schedule (if present)
|
|
|
|
### Units
|
|
|
|
2. Read about the project specifications and construction type
|
|
* partition framing
|
|
* stud material (wood or metal)
|
|
* stud depth
|
|
* wiring methods (NM or MC)
|
|
* wiring device plates (decora or standard)
|
|
* wiring device specs (are 15A devices allowed or minimum N5-20R)
|
|
* equipment (20A Kitchen and bath)
|
|
|
|
### Electrical
|
|
|
|
1. Locate Equipment Schedules
|
|
|
|
### Fixtures
|
|
|
|
1. Read about the project specifications and construction type
|
|
2. In drawings, locate:
|
|
* Fixture Schedule
|
|
* Reflected Ceiling Plans
|
|
|
|
### Low Voltage
|
|
|
|
1. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
|
|
* Cabling
|
|
* Conduit & Pathways
|
|
* Sleeving
|
|
|
|
2. In the drawings, locate:
|
|
* Floor plans where LV scope is shown
|
|
* LV Details
|
|
|
|
### Telecom
|
|
|
|
1. Locate MDF (aka MTR, MPOE) and IDF Rooms
|
|
2. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
|
|
* Cabling
|
|
* Conduit & Pathways
|
|
* Sleeving
|
|
3. Locate which plans the LV is taken off on
|
|
4. Locate LV Details
|
|
5. Read about the project specifications and construction type
|
|
6. Assume 28" MSDE if not specified.
|
|
|
|
## Voltage Drop
|
|
|
|
Unless explicitly stated in the plans or specs,
|
|
conductors are to be sized according to the relevant schedule,
|
|
_without respect for voltage drop_.
|
|
|
|
%%
|
|
TODO: Create flow chart for wiring methods.
|
|
Some cases to mention:
|
|
* Deck thickness (minimum 3x conduit outer diameter)
|
|
* Renovations (can't route in existing slabs)
|
|
%%
|