id: 2026-03-26T14:10:46-0400
|
|
title: 2026-03-26 14:10:46
|
|
tags:
|
|
- status/draft
|
|
- occupational
|
|
date-created: 2026-03-26T14:10:46-04:00
|
|
daily: "[[2026-03-26]]"
|
|
---
|
|
# 2026-03-26 14:10:46
|
|
|
|
## 1990 K Street: ConEst Manager Review
|
|
|
|
[[conest-manager-review]] for [[1990-k-street]]
|
|
lead by Josh Ford and [[joel-jansen]]
|
|
|
|
### Purpose of ConEst Manager Review
|
|
|
|
Josh explains purpose of this review to PE
|
|
|
|
Jobs below 12% margin
|
|
are reviewed further with [[corwin-fluit]]
|
|
who is able and authorized
|
|
to "make judgement calls" on pricing concerns
|
|
in order to get GP to an acceptable number.
|
|
|
|
PDI MC Cable pricing is market rate,
|
|
we have vendor specific pricing with Southwire
|
|
up to 20% lower
|
|
|
|
### Switchgear
|
|
|
|
Josh will usually not review switchgear takeoff
|
|
unless there is significant difference from labor plan
|
|
|
|
### Primaries & Secondaries
|
|
|
|
Where PEPCO is the power utility:
|
|
typically own nothing for primaries
|
|
conduit only for secondaries.
|
|
|
|
Confirmed for 1990.
|
|
|
|
### VE's To Be Incorporated Later
|
|
|
|
* Wire feeders ILO busduct
|
|
|
|
### Feeders
|
|
|
|
Fire pump feeds are not tagged as 2hr rated
|
|
takeoff assumed 2hr rated MC cable ("Vitalink")
|
|
to be confirmed with [[christian-pereiro]].
|
|
|
|
### EV Chargers
|
|
|
|
EV Chargers were erroneously placed in `System` "EL - Electrical".
|
|
|
|
### Lighting Controls
|
|
|
|
Josh was looking for for energy code
|
|
not present in pre-takeoff email or OneNote.
|
|
|
|
ASHRAE 2016
|
|
|
|
***
|
|
|
|
Follow-up to [[2026-03-26_08-49-49#Lighting Control Assemblies]].
|
|
|
|
Josh confirmed the switch to complete-furnish assemblies was appropriate.
|
|
|
|
### Labor Plan
|
|
|
|
Garage Slab/Deck is $1.30/sf
|
|
where $1.00/sf was expected.
|
|
Josh attributes this mainly to the EV chargers and CO system.
|
|
|
|
Innerduct: Use 3hrs per Unit.
|
|
|
|
### Scratch
|
|
|
|
Composite Cleanup is based on 8hrs per week for every 10 crew
|
|
|
|
Coordination Study: Expect $15k per $10m of switchgear package
|
|
|
|
#### Temporary Lighting
|
|
|
|
Temp lighting budget does not include heating
|
|
or lighting in units ("task lighting")
|
|
|
|
#### Rigging
|
|
|
|
3rd party rigging quotes are only for special cases.
|
|
It is expected that the GC's crane
|
|
can be used to set switchboards and generators.
|
|
|
|
On 1990, the GC (Clarke) RFP provides 16 hours crane time.
|