# 2026-04-01 13:56:44
|
|
|
|
### Charlotte South End Hotel: ConEst Manager Review
|
|
|
|
[[conest-manager-review]] for [[charlotte-south-end-hotel]]
|
|
lead by [[josh-ford]],
|
|
attended by [[joel-jansen]] and myself.
|
|
|
|
#### Feeders
|
|
|
|
"MSA TO BUSDUCT"
|
|
needs more elbows: added.
|
|
Josh talked about necessary pullboxes,
|
|
but they were not added.
|
|
Josh stated the purpose of the closeout budget
|
|
is to prevent procurement from buying sizes
|
|
that may be chosen arbitrarily.
|
|
Added $5,000 to the budget.
|
|
|
|
Concern was expressed
|
|
that feeders up from Main Elec may need to be lengthened
|
|
to follow MSA TO BUSDUCT routing shown on floor plans.
|
|
|
|
***
|
|
|
|
> [!quote] Josh Ford
|
|
> I really like that your feeders are whole numbers, that's nice.
|
|
|
|
***
|
|
|
|
Generator control wiring missing?
|
|
may be taken off as mech?
|
|
not resolved, moved on?
|
|
|
|
#### Subfeeds
|
|
|
|
##### Unit Mech Connections
|
|
|
|
concern that subfeeds may be double dipping
|
|
suggest decreasing if tightening is needed
|
|
|
|
##### Routing
|
|
|
|
Josh complemented subfeed routing:
|
|
"That's taking pride in your work."
|
|
|
|
I have had hesitation that it was worth doing,
|
|
if someone told be it was a waste of time,
|
|
I would not have been inclined to disagree.
|
|
|
|
#### Units
|
|
|
|
Unit receptacles are shown controlled by master switch system.
|
|
I assumed full control (not half) so no made no consideration in takeoff.
|
|
Approved.
|
|
|
|
#### Lighting Control
|
|
|
|
DO NOT USE `System` "LV - Lighting Controls System" EVER
|
|
|
|
#### My Mistakes
|
|
|
|
> [!failure]
|
|
> Port Cochere was taken off as Exterior Amenity.
|
|
> Joel corrected this without telling me.
|
|
|
|
> [!failure]
|
|
> Missed unit occupancy sensors
|
|
|
|
#### Closeout
|
|
|
|
> [!quote] Josh Ford
|
|
> We're carrying material handling
|
|
> because we own fixtures and its a tall building
|
|
|
|
#### Labor Plan
|
|
|
|
\$1.41 per sf garage, expected ~\$1.00
|
|
|
|
***
|
|
|
|
0.182 hrs/sf seems incredibly high,
|
|
expected ~0.120.
|
|
|
|
#### Aside
|
|
|
|
> [!aside]
|
|
> [[estimating-golf]] question:
|
|
> "you only have one main switchboard?"
|
|
|
|
***
|
|
|
|
Josh found the answer to a question of scope
|
|
in the qualifications of [[pdi-bid-estimating|Bid]]'s proposal.
|
|
he said he did not immediately think to look for them
|
|
because they are rare of current proposals.
|
|
Apparently they are penalized by the Proposal Audit Scorecard.
|
|
"They wanted it uniform so they stopped putting qualifications on proposals"
|
|
|
|
***
|
|
|
|
[[megan-blizard]]
|