# 2026-04-27 12:56:35
## Virginia Live! Internal Review
review of [[virginia-live-casino-and-hotel]] [[accubid|Accubid]] job
with [[pdi-operations|Ops]]
Underfloor power is Reloc.
Customer is curious if it would be more cost effective to use MC.
### Meeting Objective
discuss closeout mainly:
quotes and subs.
### Topics Discussed
#### Fixture Labor
> **Furniture, Fixtures, and Equipment (FF&E)**
Concern that all fixtures are captured
"add a line for aiming and testing"
1 week (80 hours)
#### Shift Rate
"in the past we've paid a little more for night work,
but nothing crazy"
#### Site Services
$2,500 per day scaffold
Ditch witches for most excavation
idea floated to buy equipment rather than rent
bobcat
wire puller
hydraulic bender
Do we own dewatering?
pretty sure yes
#### MV Terminations
No one at PDI can perform MV terms
so they must be subbed out
worst case $300k
9 terms $60k
to be quoted by Ops
#### Testing
primary injection testing
NETA testing
to be quoted by Ops
#### Rigging
Ops quoted $85k to take one generator off the truck.
to be quoted by Ops
#### Burden
PTO not included in burden
because it is not charged to the job
### Admin Housing
Ops paying $4,500 per month for 6-bed
#### Composite Cleanup
exact terms in contract
#### Permits
to be quoted by Ops