Subfeeds
Sequence
1. Estimate preparation
- Read about the project specifications and construction type
- Delivery Method: (Plans & Specs, Design Build, Design Assist, Preliminary Budget)
- Deck Thickness
- Corridor Ceiling type
- In the drawings, locate:
- Unit Panel Schedules
- Unit Load Calculations
- Riser Diagram
- Subfeed schedule (if present)
2. Takeoff
-
Determine wiring method
Construction Type Wiring Method Subfeed Options 1,2 MC Cable MC, PVC, EMT 3,4,5 NM Cable SER, EMT %% TODO: Create flow chart for wiring methods. Some cases to mention:
- Deck thickness (minimum 3x conduit outer diameter)
- Renovations (may not be able to run in slab) %%
-
Route subfeeds to the Meter Centers using appropriate adder lengths
Tip
Identify if and where typicals can be used
-
Assign material to lengths and apply Voltage drop if applicable
-
Pigtails and Wireway Troughs if applicable
3. Extension (Review and Checking)
- Use the extension tab to determine the Correct Quantity