# Subfeeds
## Sequence
### 1. Estimate preparation
1. Read about the project specifications and construction type
* Delivery Method: (Plans & Specs, Design Build, Design Assist, Preliminary Budget)
* Deck Thickness
* Corridor Ceiling type
2. In the drawings, locate:
* Unit Panel Schedules
* Unit Load Calculations
* Riser Diagram
* Subfeed schedule (if present)
### 2. Takeoff
1. Determine wiring method
| Construction Type | Wiring Method | Subfeed Options |
| ----------------- | ------------- | --------------- |
| 1,2 | MC Cable | MC, PVC, EMT |
| 3,4,5 | NM Cable | SER, EMT |
%%
TODO: Create flow chart for wiring methods.
Some cases to mention:
* Deck thickness (minimum 3x conduit outer diameter)
* Renovations (may not be able to run in slab)
%%
2. Route subfeeds to the Meter Centers using appropriate adder lengths
> [!tip]
> Identify if and where typicals can be used
3. Assign material to lengths and apply Voltage drop if applicable
4. Pigtails and Wireway Troughs if applicable
### 3. Extension (Review and Checking)
1. Use the extension tab to determine the Correct Quantity