1.1 KiB
1.1 KiB
id, aliases, tags
| id | aliases | tags | |
|---|---|---|---|
|
Switchgear
Sequence
1. Estimate preparation
- Initial the OneNote
- In the drawings, locate:
- Riser Diagrams
- House Panels
- Copy over the Temporary assemblies from "Ben -1"
2. Takeoff
-
Build Items in Distribution:
- Panelboards
- Switchboards
- Transfer SWs
- Meter centers
- Generator
-
Takeoff Common Assemblies:
- XFMRs
- Disconnect Switches
- Bus Duct
-
Takeoff Items in Item Database:
- Wireway (Trough/Gutter)
-
Takeoff Temp Assemblies:
- CT Cabinet
- Meter
- Fire Pump
- Fire Pump Controller
- SPD/TVSS
When building panelboards/switchboards, add terminations according to an example from the schedules. Do not include feeder terminations.
Items to Avoid:
- Tap Boxes
- Bus Duct
- Vault Room
- Anything FPL
- Grounding
- Elevator Room
Generator
3. Extension (Review and Checking)
- Generator
- Ensure takeoff is in the generator Area and System breakdowns
- Put location, quantity, and type on OneNote