Sequence

1. Estimate preparation

  1. Initial the OneNote
  2. In the drawings, locate:
    • Riser Diagrams
    • House Panels
  3. Copy over the Temporary assemblies from "Ben -1"

2. Takeoff

  1. Build Items in Distribution:

    • Panelboards
    • Switchboards
    • Transfer SWs
    • Meter centers
    • Generator
  2. Takeoff Common Assemblies:

    • XFMRs
    • Disconnect Switches
    • Bus Duct
  3. Takeoff Items in Item Database:

    • Wireway (Trough/Gutter)
  4. Takeoff Temp Assemblies:

    • CT Cabinet
    • Meter
    • Fire Pump
    • Fire Pump Controller
    • SPD/TVSS

When building panelboards/switchboards, add terminations according to an example from the schedules. Do not include feeder terminations.

Items to Avoid:

  • Tap Boxes
  • Bus Duct
  • Vault Room
  • Anything FPL
  • Grounding
  • Elevator Room

Generator

3. Extension (Review and Checking)

  1. Generator
    • Ensure takeoff is in the generator Area and System breakdowns
    • Put location, quantity, and type on OneNote