## Sequence
|
|
|
|
### 1. Estimate preparation
|
|
|
|
1. Initial the OneNote
|
|
2. In the drawings, locate:
|
|
* Riser Diagrams
|
|
* House Panels
|
|
3. Copy over the Temporary assemblies from "Ben -1"
|
|
|
|
### 2. Takeoff
|
|
|
|
1. Build Items in Distribution:
|
|
* Panelboards
|
|
* Switchboards
|
|
* Transfer SWs
|
|
* Meter centers
|
|
* Generator
|
|
|
|
2. Takeoff Common Assemblies:
|
|
* XFMRs
|
|
* Disconnect Switches
|
|
* Bus Duct
|
|
|
|
3. Takeoff Items in Item Database:
|
|
* Wireway (Trough/Gutter)
|
|
|
|
4. Takeoff Temp Assemblies:
|
|
* CT Cabinet
|
|
* Meter
|
|
* Fire Pump
|
|
* Fire Pump Controller
|
|
* SPD/TVSS
|
|
|
|
When building panelboards/switchboards,
|
|
add terminations according to an example from the schedules.
|
|
**Do not include feeder terminations.**
|
|
|
|
Items to Avoid:
|
|
* Tap Boxes
|
|
* Bus Duct
|
|
* Vault Room
|
|
* Anything FPL
|
|
* Grounding
|
|
* Elevator Room
|
|
|
|
#### Generator
|
|
|
|
### 3. Extension (Review and Checking)
|
|
|
|
1. Generator
|
|
* Ensure takeoff is in the generator Area and System breakdowns
|
|
* Put location, quantity, and type on OneNote
|