# Pre-Takeoff Confirmation
The purpose of the pre-takeoff confirmation
is to address potential discrepancies
between the requirements of the project documents
and the scope included in the bid team's proposed price.
## Procedure
### Complete the Template
Complete [[conest-pre-takeoff-email-template|the template]]
for the project.
Direction is included in comments.
### Send the Email
Paste the completed template content to the body of a new email.
**Subject:** "Pre-Takeoff Confirmation - ..."
**To:**
* Preconstruction Manager %% Brian %%
* Senior Bid Estimator %% Christian %%
* Bid Estimator or Associate Estimator (if applicable)
**CC:**
* Senior Construction Estimator %% Joel %%
* ConEst Manager (Josh Ford)
* Director of Estimating (Corwin Fluit)
* Jessalyn Williams
* Other ConEst Estimators (if applicable)
[^1]: [[2026-03-20_09-11-09#Pre-Takeoff Email Process]]