# 2026-06-03 14:05:39
|
|
|
|
## 303 Mariposa Residence Senior Review
|
|
|
|
[[conest-senior-review]] for [[303-mariposa-residence]]
|
|
lead by [[joel-jansen]] and attended by [[zane-meyers]] and [[jared-defanti]].
|
|
|
|
### Selling Price
|
|
|
|
[[pdi-bid-estimating|Bid]]'s proposal base bid was \$800,000,
|
|
but in response to the [[conest-pre-takeoff-confirmation]]
|
|
[[joshua-komis]] said to add \$65,000 for secondaries.
|
|
|
|
We found correspondence
|
|
that the secondaries were sold as $10,000 for conduit
|
|
and $65,000 for wire.
|
|
|
|
Joel messaged Komis to clarify.
|
|
He responded to use \$875,000.
|
|
|
|
### Site Run Adders
|
|
|
|
Joel questioned the use of 15ft adders for secondaries.
|
|
I explained their use was based on prior direction he had given below.
|
|
|
|
> [!quote] feeders-takeoff.md
|
|
> #### Adders
|
|
>
|
|
> Use the difference in elevation between equipment
|
|
> or 10ft, whichever is greater.
|
|
>
|
|
> Add an additional 5ft (total 15ft) for site runs
|
|
> (primaries, secondaries, etc.).
|
|
|
|
Joel remembered and started to move on.
|
|
Jared asked if the extra adder was for vertical distance or routing contingency,
|
|
Joel responded that it was sort of both.
|
|
|
|
I suggested that if it may be necessary to adjust them anyway,
|
|
and "site runs" often being up to interpretation,
|
|
it may be preferable to assume 10ft to start for all cases
|
|
where the start and end are on the same level.
|
|
That is, remove the conditional 5ft extra adder from the script.
|
|
Joel agreed.
|
|
|
|
Mariposa's site runs didn't need adders at all
|
|
since we added PVC80 stub-ups.
|
|
|
|
### Site Low Voltage Duct Bank
|
|
|
|
We assumed 2in conduit,
|
|
but did not note this visibly.
|
|
|
|
### Solar Feeders
|
|
|
|
Solar [[feeders-takeoff]] used copper feeder size
|
|
based on aluminum size shown in Solar set.
|
|
No change necessary.
|
|
|
|
We should have added the solar one-line to LiveCount.
|
|
|
|
### Material Pricing
|
|
|
|
Joel requested pricing for the dimmable receptacles from [[pdi-procurement]].
|
|
|
|
### Mechanical Connections
|
|
|
|
B-1, B-2 feeders were parallel runs,
|
|
but taken off as 2 counts each.
|
|
|
|
### Telecom
|
|
|
|
[[telecom-takeoff]] assumed Cat5e
|
|
but we did not note the assumption visibly.
|
|
|
|
### Fire Alarm
|
|
|
|
[[fire-alarm-takeoff]]
|
|
|
|
> PCM is supposed to keep Systems from
|
|
|
|
\$10,000 was my budget
|
|
assuming a dozen or so interconnected smokes.
|
|
|
|
\$26,XXX was the quote
|
|
for sprinkler monitoring only.
|
|
"only one assembly"
|
|
|
|
### Closeout
|
|
|
|
#### Final Pricing
|
|
|
|
[[pdi-accubid-final-price]]
|
|
|
|
##### Sales Tax
|
|
|
|
10.35%
|
|
|
|
#### Equipment
|
|
|
|
#### General Expenses
|
|
|
|
"Just the PM so we only need one trip"
|
|
|
|
Got rid of APM, Foreman
|
|
|
|
Approved Labor Plan created by Bid,
|
|
approved by (Efren's title)
|
|
|
|
only 3mil or above
|
|
|
|
coordination study
|
|
\$15,000 up to x
|
|
\$25,000 above x
|