title: Lightning Protection Takeoff
|
|
tags:
|
|
- occupational/takeoff
|
|
- status/draft
|
|
- type/guide
|
|
up: "[[takeoff-scripts]]"
|
|
aliases:
|
|
- lightning protection takeoff
|
|
---
|
|
# Lightning Protection Takeoff
|
|
|
|
> [!info]
|
|
> See [[lightning-protection]] for more on lightning protection systems.
|
|
|
|
> [!important] ConEst Scope
|
|
> Lightning protection takeoff may or may not be necessary,
|
|
> see proposal on [[pdi-bpm|BPM]].
|
|
> Only takeoff if LP is included in the base bid.
|
|
|
|
### Subcontractors
|
|
|
|
Find lightning protection subcontractor quotes on BPM,
|
|
search for direction on downlead counts, total length, and conduit size
|
|
|
|
> [!example]
|
|
> Contractor to furnish 1,980' of 1" PVC conduit and pull string
|
|
|
|
> [!tip]
|
|
> While you have the quotes open,
|
|
> put the costs in the Subcontractors tab in [[accubid|Accubid]].
|
|
|
|
If no quote is available:
|
|
|
|
* **Downlead locations** = building corners + additional locations
|
|
such that downlead spacing is not greater than 100ft
|
|
* Minimum 10 locations for High-rise
|
|
|
|
* **Total downlead conduit length** = building height * downlead locations
|
|
|
|
* **Conduit size** = 1-1/4"
|
|
|
|
### Takeoff
|
|
|
|
> * `Area` = "01 - Lightning Protection Building"
|
|
> * `Phase` = "Building - BOH, Storage & Common"
|
|
> * `System` = "LPT - Lightning Protection"
|
|
> * `BidItem` = "3 - Building"
|
|
|
|
* Takeoff: `COMMON ASSEMBLIES`/`PDI EMPTY CONDUIT`/`PVC ASSEMBLIES`/`* CONDUIT - PVC40`
|
|
* **Length** = total downlead conduit length
|
|
* **Count** = downlead locations
|
|
|
|
* Add item: `ITEM DATABASE`/`BOXES & CABINETS`/`JUNCTION BOXES AND INDUSTRIAL CABINETS`/
|
|
`BOXES - HNGD CVR - PAINTED STEEL - NEMA 1`/` 6x 4x 4" BOX HNGD CVR - NEMA 1`
|