id: electrical
|
|
aliases: []
|
|
tags:
|
|
- systems/electrical
|
|
---
|
|
# Electrical
|
|
|
|
## Info
|
|
|
|
### Lighting Control
|
|
|
|
By PDI convention, [child:: [[lighting-controls]]] are generally "Electrical", not "Lighting".
|
|
|
|
## Sequence
|
|
|
|
### 1. Estimate preparation
|
|
|
|
1. Read about the project specifications and construction type
|
|
2. Locate Equipment Schedules
|
|
3. Device specs (Decora or Standard)
|
|
|
|
### 2. Takeoff
|
|
|
|
1. Takeoff all equipment that is not #12
|
|
2. Go by Drawing in chronological order
|
|
3. Takeoff Enlarged Drawings
|
|
4. Do final checklist in electrical takeoff notes
|
|
|
|
> [!tip]
|
|
> It is sometimes easier to rebuild a designation than to modify it.
|
|
> For designations with existing takeoffs, Right-Click > `Empty Designation`.
|
|
> The build process can then be completed anew.
|
|
|
|
#### Mechanical Connections
|
|
|
|
##### CU/IP
|
|
|
|
* Units Condensing Unit
|
|
* Mechanical Connection
|
|
|
|
##### Trash Chute
|
|
|
|
Horizontal:
|
|
* Check if shown on power drawings as mech connection
|
|
* If not, use 100ft length
|
|
|
|
Vertical (Riser):
|
|
* Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...`
|
|
* Uncheck Link 'Enable Livecount'
|
|
* Takeoff in Typical
|
|
* Length = average floor to floor height
|
|
|
|
### 3. Extension (Review and Checking)
|
|
|
|
1. Count Car chargers and location
|