# Project Start Notification
Save all documents below to ".\8. PSN Docs"
## Feeder Verification
For `System` = "FRR - Feeders and Risers", "PRI - Primaries", and "SEC - Secondaries"
1. Filter Takeoff by `System`
2. Copy and paste all lines to Excel
3. Remove all columns except _Description_, _Length_, and _Count_
4. Make a note of any typicals
5. Repeat process for systems
Save to ".\8. PSN Docs\ ... - Feeder Verification.xlsx"
## Procurement Export
Accubid Export Extension only to Excel.
Group by `System`, `PDI SORT CODES`.
## WBS
"S:\Estimating\19 WBS Agreement GP\4. Award Agreement WBS\ ..."
Export Awarded WBS to PDF, or just copy if available.
## CBOM
Accubid full export to Excel.
Group by `Bid Item`, `System`, `PDI SORT CODES`, `Area`, `Phase`.
Save to ".\6. Notes & Emails\Accubid CBOM - ..."
Open Award Agreement WBS
"S:\Estimating\19 WBS Agreement GP\4. Award Agreement WBS\ ..."
%%
"CBOM Import" something or other
%%
Do not save the WBS.
Delete labor-only tabs:
* "Lighting"
* "SwitchGear"
* "Generator"
## Labor Plan
Copy ConEst Labor Plan
".\1. Labor Plan & Estimate\ConEst Labor Plan ..."
## Unit Matrix
Save as Excel with only unit matrix.
Remove area breakouts, etc.
## Distribution List
"S:\Estimating\7 ConEst Team\ConEst Process Documents\PSN Documents Distribution List.xlsx"
Email Distribution List:
* To: PM, PX, RVP, SVP, Super
* CC: Commodities Buyer, Procurement PX, ITR Team, PCO Team, ConEst Manager, Jessalyn Williams
Reach out to Chief's Coordinator for PSN Summary Chart to get list of PM & PX