# Misc Budgets
## Slab Deck
* `System` = "Electrical"
Create `area` Typicals for every concrete slab floor:
* 'All Building'
* 1 each level except roof
* **HD:** 1 per Section
* 'All Garage'
* 1 each level
In each Typical:
* Takeoff: `ITEM DATABASE`/`MISC PDI PRODUCT`/`MISC MATERIAL - SLAB/DECK & FEEDER`/`MISC MATERIAL - SLAB/DECK (NAILS, PAINT, TAPE, ETC = $250)`
* 1 Takeoff each Typical
* _Count_ = 1
## Temporary Power & Lighting
### Temp Power
```
Area = "2 - Site"
Phase = "Temp Power"
System = "TPS - Temp Power Service (Site)"
BidItem = "1 - Site"
```
* Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - * SERVICE`
### Temp Lighting (Building)
```
Area = "01 - Temp Power Distribution Building"
Phase = "Temp Power"
System = "TPD - Temp Power Distribution (Gag. & Bldg.)"
BidItem = "3 - Building"
```
* Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)`
* _Count_ = Building GSF = Total GSF - Garage GSF
Garden Styles:
* Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - T POLE (EACH)`
* _Count_ = 1 per 150ft per building
### Temp Lighting (Garage)
```
Area = "01 - Temp Power Distribution Building"
Phase = "Temp Power"
System = "TPD - Temp Power Distribution (Gag. & Bldg.)"
BidItem = "3 - Building"
```
* Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)`
* _Count_ = Garage GSF
## Irrigation Pumps
```
Area = "2 - Site"
Phase = "Temp Power"
System = "MISC - Site Miscellaneous"
BidItem = "1 - Site"
```
* (3) 3Phase 30A 200' Mech. Con. EMT Carflex
* Append to name: "Irrigation Pump - "