# Low Voltage
|
|
|
|
## Sequence
|
|
|
|
### 1. Estimate preparation
|
|
|
|
## Telecom - Riser
|
|
|
|
1. Service entrance conduit "Site Low Voltage Ductbank (SLVDB)"
|
|
2. Riser throughout building
|
|
3. Sleeving for riser
|
|
|
|
## Telecom - Devices
|
|
|
|
1. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
|
|
* Cabling
|
|
* Conduit & Pathways
|
|
* Sleeving
|
|
2. Locate which plans the LV is taken off on
|
|
3. Locate LV Details
|
|
4. Read about the project specifications and construction type
|
|
5. Fill out OneNote
|
|
|
|
### 2. Takeoff
|
|
|
|
1. Takeoff devices as shown throughout the building
|
|
2. Takeoff Conduit Riser as needed
|
|
|
|
### 3. Extension (Review and Checking)
|
|
|
|
1. Sleeving
|
|
|
|
## Low Voltage
|
|
|
|
### 1. Estimate preparation
|
|
|
|
1. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
|
|
* Cabling
|
|
* Conduit & Pathways
|
|
* Sleeving
|
|
2. In the drawings, locate:
|
|
* Floor plans where LV scope is shown
|
|
* LV Details
|
|
3. Read about the project specifications and construction type
|
|
4. Fill out OneNote
|
|
|
|
### 2. Takeoff
|
|
|
|
1. Takeoff devices as shown throughout the building
|
|
2. Takeoff riser conduit as needed
|
|
|
|
### 3. Extension (Review and Checking)
|
|
|
|
1. Sleeving for riser
|