title: Fire Alarm Takeoff
|
|
tags:
|
|
- occupational/takeoff
|
|
- status/draft
|
|
- type/guide
|
|
up: "[[takeoff-scripts]]"
|
|
aliases:
|
|
- fire alarm takeoff
|
|
---
|
|
# Fire Alarm Takeoff
|
|
|
|
> [!important]
|
|
> Complete [[conest-emergency-systems-research]] before beginning takeoff.
|
|
|
|
> [!info]
|
|
> This note is intended for practice specific to [[pdi-estimating]].
|
|
> See [[fire-alarm]] for information about fire alarm systems.
|
|
|
|
* `System` = "FA - Fire Alarm"
|
|
|
|
## Assembly Selection
|
|
|
|
Free Air < PVC in Slab < EMT
|
|
|
|
* _High Rise (Steel & slab):_ Free air in Units, use conduit elsewhere.[^1]
|
|
* _Mid Rise, High Density (Wood frame):_ Free air, conduit only where required.
|
|
|
|
[^1]: [[2026-02-26_10-06-19]]
|
|
|
|
## Backbone
|
|
|
|
Include [[sleeving-takeoff]] as necessary.
|
|
|
|
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/...
|
|
|
|
### Fire Command Center
|
|
|
|
1. * `Area` = As shown.
|
|
* `Phase` = As shown.
|
|
|
|
.../`HEAD END EQUIP`/`... HEAD END`
|
|
|
|
### Generator Room
|
|
|
|
1. * `Area` = Same as FACR.
|
|
* `Phase` = Same as FACR.
|
|
|
|
.../`GEN, ELEV, FIRE PUMP & FA ROOM ASSEMBLIES`/`GENERATOR ROOM ...`
|
|
|
|
### Fire Pump Room
|
|
|
|
1. * `Area` = Same as FACR.
|
|
* `Phase` = Same as FACR.
|
|
|
|
.../`GEN, ELEV, FIRE PUMP & FA ROOM ASSEMBLIES`/`FIRE PUMP ROOM ...`
|
|
|
|
### Elevator Control Rooms
|
|
|
|
> Also "Elevator Machine Room (EMR)"
|
|
|
|
* `Area` = Same as FACR.
|
|
* `Phase` = Same as FACR.
|
|
|
|
For each Elevator Control Room (ECR):
|
|
|
|
1. .../`GEN, ELEV, FIRE PUMP & FA ROOM ASSEMBLIES`/`ELEV CONTROL ROOM ...`
|
|
* **Count** = 1
|
|
|
|
2. .../`GEN, ELEV, FIRE PUMP & FA ROOM ASSEMBLIES`/`FACR TO ELEV CONTROL RM ...`
|
|
* **Length** = Length measured from the most distant points of the FACR and ECR.
|
|
* Input adder length to reach the level of the ECR (Minimum 15ft).
|
|
|
|
### Elevator Shafts
|
|
|
|
* `Area` = Same as FACR.
|
|
* `Phase` = Same as FACR.
|
|
|
|
For each elevator shaft:
|
|
|
|
1. .../`GEN, ELEV, FIRE PUMP & FA ROOM ASSEMBLIES`/`ELEV SHAFT ...`
|
|
* **Count** = 1
|
|
|
|
2. .../`GEN, ELEV, FIRE PUMP & FA ROOM ASSEMBLIES`/`FACR TO ELEV SHAFT ...`
|
|
* **Length** = Length measured from the most distant points of the FACR and elevator shaft.
|
|
* Input adder length to reach the level of the shaft (Minimum 15ft).
|
|
|
|
> [!important] Counting Elevator Shafts
|
|
> Adjacent elevators may be in the same or parallel shafts.
|
|
> Count the shafts accordingly:
|
|
>
|
|
> ```none
|
|
> +-----------------------------+--------------------------------+
|
|
> | | |
|
|
> | || +--------+ +--------+ || | || +--------+ || +--------+ || |
|
|
> | || | Elev 1 | | Elev 2 | || | || | Elev 1 | || | Elev 2 | || |
|
|
> | || +--------+ +--------+ || | || +--------+ || +--------+ || |
|
|
> | ||=======================|| | ||============||============|| |
|
|
> | 1 shaft | 2 shafts |
|
|
> +-----------------------------+--------------------------------+
|
|
> ```
|
|
|
|
### FACR to Stairwells
|
|
|
|
> [!info]
|
|
> This is for the Flow/Tamper modules in the stairwells
|
|
|
|
For each stairwell:
|
|
|
|
1. * `Area` = Same as FACR.
|
|
* `Phase` = Same as FACR.
|
|
|
|
.../`GEN, ELEV, FIRE PUMP & FA ROOM ASSEMBLIES`/`FACR TO STAIRWELLS 1" CONDUIT ...`
|
|
* **Length** = Length measured from the most distant points of the FACR and stairwell.
|
|
* Input adder length to reach the level of the stairwell (Minimum 15ft).
|
|
|
|
## Terminal Cabinets
|
|
|
|
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`TERMINAL CABINET`/`ACE D ACCESSORY CABINET ENCLOSURE ...`
|
|
|
|
* _Garden Style, High Density:_ (2) 1"C
|
|
* _High Rise:_ (2) 2"C
|
|
|
|
1. Horizontal:
|
|
|
|
* `Area` = Same as FACR.
|
|
|
|
`... HORIZONTAL RUN`
|
|
* **Length** = Length measured from FACR to all electrical rooms
|
|
|
|
2. Vertical:
|
|
|
|
* `Area` = "Typical - Building All Levels"
|
|
|
|
`... RISER`
|
|
* **Length** = 10ft
|
|
|
|
> [!important]
|
|
> [[sleeving-takeoff]]
|
|
|
|
## Annunciator Panels
|
|
|
|
> [!info] Also Known As
|
|
> * Fire Alarm Annunciator (FAA)
|
|
> * Fire Alarm Annunciator Panel (FAAP)
|
|
|
|
1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`ANNUNCIATORS`/`REMOTE SERIAL ANNUNCIATOR ...`
|
|
* **Length** = Length measured from the FACR to FAA or Lobby
|
|
|
|
## Central Monitoring Loop
|
|
|
|
* `System` = "FAR - Fire Alarm Loop"
|
|
|
|
> [!important]
|
|
> Garden Style only.
|
|
>
|
|
> Fire Alarm Control Panels from each building will send a signal to a central location.
|
|
>
|
|
> In case of an emergency,
|
|
> the fire department will go to the central fire alarm station
|
|
> and find out what the issue is.
|
|
|
|
## Devices
|
|
|
|
Takeoff should always(?) use the
|
|
`DOES NOT INCLUDE COST OF DEVICES AND CABLE` assemblies,
|
|
since we will always(?) have a fire alarm quote.
|
|
|
|
### Smoke Detectors
|
|
|
|
1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`INITIATING DEVICES WITH WIRE - ...`/`SMOKE DETECTOR W/ BASE - ...`
|
|
* **Count:** As shown, otherwise (1) every stairwell at every level.
|
|
|
|
### Pull Stations
|
|
|
|
1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`INITIATING DEVICES WITH WIRE - ...`/`PULL STATION - ...`
|
|
* **Count:** As shown, otherwise (1) every stairwell at every level and every exterior exit.
|
|
|
|
### Flow/Tamper Switches
|
|
|
|
1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`INITIATING DEVICES ...`/`ADDRESSABLE DUAL MONITOR MODULE - FLOW/TAMPER - ...` (No free-air)
|
|
* **Count:** As shown, otherwise (1) every stairwell at every level.
|
|
|
|
### Magnetic Door Holders
|
|
|
|
1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`INDICATING DEVICES WITH WIRE - ...`/`MAGNETIC DOOR HOLDER - ...`
|
|
* **Count:** As shown, otherwise (2) every set of double doors.
|
|
(Typical of elevator lobbies and corridors)
|
|
|
|
### Horns, Speakers, and Strobes
|
|
|
|
1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`INDICATING DEVICES WITH WIRE - ...`/`INDOOR HORN STROBE - ...`
|
|
|
|
_Design Build (method 1):_
|
|
* Count every 75 ft,
|
|
* measure with circles on Bluebeam
|
|
* or divide relevant SF area by 4415[^2]
|
|
* every elevator lobby, and
|
|
* every BOH room on the first floor and garage levels.
|
|
|
|
[^2]: $\pi(\frac{75}{2})^2 \approx 4415$
|
|
|
|
_Design Build (alternative method):_
|
|
* 15ft from end of corridor,
|
|
* then every 50ft
|
|
|
|
## Fire/Smoke Dampers (FSD's)
|
|
|
|
> [!info]
|
|
> Refers to fire, smoke, and combination fire/smoke dampers.
|
|
|
|
In [[pdi-building-types#High Rise|high-rise construction]],
|
|
usually found on every level with units.
|
|
|
|
> [!tip]
|
|
> If possible, use
|
|
> * `Area` = "Typical - Fire Smoke Dampers"
|
|
> with quantity per level as shown.
|
|
|
|
For each damper, take off both
|
|
|
|
1. * `System` = "FA - Fire Alarm"
|
|
|
|
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`INITIATING DEVICES ...`/`ADDRESSABLE OUTPUT RELAY CONTROL MODULE ...`
|
|
|
|
2. * `System` = "EL - Electrical"
|
|
|
|
`COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`FSD ...`
|