# PDI Labor Plan
|
|
|
|
1. Fill out project basics
|
|
|
|
2. Check that everything is sorted into correct `Phase` and `Area` (Extension: Phase - Area)
|
|
|
|
3. Move everything in BUILDING FA systems into FA phase
|
|
|
|
* Create `Phase` = "Fire Alarm"
|
|
* Check `System` and `Bid Item`
|
|
* Scroll through each and select all line items `FA - ...`
|
|
* Set `Phase` = "Fire Alarm"
|
|
|
|
4. Separate all Phases into their proper corresponding `Labor Factor`
|
|
|
|
* Scroll through each `Phase`
|
|
* Change breakdown of everything in each phase to the proper `Labor Factor`
|
|
* Do not move Temp Power (budgets) or site
|
|
|
|
5. Use the [[accubid|Accubid]] Extension tab to fill out the "Unit Lbr Calc" tab in the labor plan
|
|
|
|
6. Select extension view "Phase, Sort Code"
|
|
|
|
7. Open `Phase` "UNIT RESIDENTIAL" and "Building - Corridors"
|
|
|
|
8. Go into each Sort code to find the count for each unit item
|
|
|
|
| Code | Description |
|
|
| ---- | -------------------- |
|
|
| 200 | rough |
|
|
| 300 | trim |
|
|
| 400 | rough wire and cable |
|
|
|
|
9. Some items will autofill when you fill out the "Accubid Extension Totals" table on the right
|
|
|
|
* Anything you make adjustments to, highlight red so it can be reviewed
|
|
|
|
10. Fill out the "Labor for Concrete Slab/Deck Labor" table on the labor sheet calc tab
|
|
|
|
* For the floor counts, if there are multiple buildings, add their total level count together
|
|
* 2 buildings that each have 10 floors, input 20 for "number of floors - building
|
|
|
|
* Add any useful description to the naming
|
|
* Can change "Other" to something more prevalent on the project
|
|
|
|
* "pour section rate" refers to the size of each slab that will be poured
|
|
* sometimes will be shown on the structural plans
|
|
|
|
* "Number of days per..." equals "Pour Section Qty" times 4 or 5
|
|
|
|
11. Check that everything is sorted into correct `Phase` and `Area` (Extension: "Phase - Area")
|