303 Mariposa Residence Senior Review

conest-senior-review for 303-mariposa-residence.

Selling Price

pdi-bid-estimating's proposal base bid $800,000

Joel messaged joshua-komis to clarify.

Site Run Adders

previous direction to use 15ft adders for site runs It would be easier to assume 10ft for all cases Joel agreed

Mariposa's site runs didn't need adders at all since we added PVC80 stub-ups.

Site Low Voltage Duct Bank

We assumed 2in conduit, but did not note this visibly.

Solar Feeders

Solar feeders-takeoff used copper feeder size based on aluminum size shown in Solar set. No change necessary.

Material Pricing

Joel requested pricing for the dimmable receptacles from pdi-procurement.

Mechanical Connections

B-1, B-2 feeders were parallel runs, but taken off as 2 counts each.

Telecom

telecom-takeoff used Cat5e which we assumed, but did not note visibly.

Fire Alarm

fire-alarm-takeoff

PCM is supposed to keep Systems from

$10,000 was my budget assuming a dozen or so interconnected smokes.

$26,XXX was the quote for sprinkler monitoring only

Closeout

Sales Tax

pdi-accubid-final-price 10.35%

Equipment

General Expenses

"Just the PM so we only need one trip"

Got rid of APM, Foreman

Approved Labor Plan created by Bid, approved by (Efren's title)

only 3mil or above

coordination study $15,000 up to x $25,000 above x